UK onshore wind farms at a glance
- Operational onshore projects
- 785
- Capacity
- 15.5 GW
- Turbines
- 7,353
- In development
- 703
696 with 2+ turbines
20.1 GW
| Nation | Projects | Capacity | Turbines |
|---|---|---|---|
| Scotland | 348 | 10,201.5 MW | 4,371 |
| England | 282 | 2,871.4 MW | 1,542 |
| Northern Ireland | 83 | 1,215.7 MW | 591 |
| Wales | 72 | 1,219.7 MW | 849 |
Largest onshore wind farms in the UK
| # | Wind farm | Capacity | Turbines | Location | Operational | Operator / applicant |
|---|---|---|---|---|---|---|
| 1 | Viking Wind Farm | 443 MW | 103 | Shetland, Scotland | 2024 | Viking Energy Wind Farm |
| 2 | Clyde Wind Farm | 350 MW | 152 | Strathclyde, Scotland | 2012 | Scottish and Southern Energy (SSE)/ Greencoat UK Wind |
| 3 | Whitelee | 322 MW | 140 | Strathclyde, Scotland | 2007 | CRE Energy/ Scottish Power |
| 4 | South Kyle Wind Farm | 240 MW | 50 | Strathclyde, Scotland | 2023 | Vattenfall |
| 5 | Kilgallioch wind farm | 239 MW | 96 | Dumfries and Galloway, Scotland | 2017 | Scottish Power Renewables |
| 6 | Pen Y Cymoedd | 228 MW | 76 | Neath Port Talbot, Wales | 2017 | Vattenfall (previously Nuon Renewables) |
| 7 | Stronelairg Wind Farm | 227.7 MW | 66 | Highland, Scotland | 2018 | Scottish and Southern Energy (SSE) |
| 8 | Dorenell Wind Farm (Previously Site A and B Scaut Hill) | 177 MW | 59 | Grampian, Scotland | 2018 | EDF Energy Renewables/ Infinergy |
| 9 | Clyde Wind Farm Extension (Clyde 2) | 172.8 MW | 54 | Strathclyde, Scotland | 2017 | Scottish and Southern Energy (SSE)/ GIB |
| 10 | Griffin Wind farm | 156 MW | 52 | Tayside, Scotland | 2012 | Greenpower (Griffin) Ltd |
| 11 | Fallago Rig | 144 MW | 48 | Borders, Scotland | 2013 | EDF Energy Renewables |
| 12 | Crystal Rig Wind Farm Phase 2a | 138 MW | 60 | Borders, Scotland | 2010 | Fred Olsen Renewables |
| 13 | Harestanes | 136 MW | 68 | Dumfries and Galloway, Scotland | 2014 | Scottish Power Renewables |
| 14 | Black Law | 124 MW | 54 | Strathclyde, Scotland | 2004 | Scottish Power Renewables |
| 15 | Arecleoch Windfarm | 120 MW | 60 | Ayrshire, Scotland | 2011 | Scottish Power Renewables |
For offshore and pipeline rankings, see the largest wind farms in the UK.
Onshore wind farms in Scotland
348 operational onshore projects, 10.2 GW. See the wind farms in Scotland guide for a map and the pipeline.
| Wind farm | Capacity | Turbines | Location | Operational | Operator / applicant |
|---|---|---|---|---|---|
| Viking Wind Farm | 443 MW | 103 | Shetland, Scotland | 2024 | Viking Energy Wind Farm |
| Clyde Wind Farm | 350 MW | 152 | Strathclyde, Scotland | 2012 | Scottish and Southern Energy (SSE)/ Greencoat UK Wind |
| Whitelee | 322 MW | 140 | Strathclyde, Scotland | 2007 | CRE Energy/ Scottish Power |
| South Kyle Wind Farm | 240 MW | 50 | Strathclyde, Scotland | 2023 | Vattenfall |
| Kilgallioch wind farm | 239 MW | 96 | Dumfries and Galloway, Scotland | 2017 | Scottish Power Renewables |
| Stronelairg Wind Farm | 227.7 MW | 66 | Highland, Scotland | 2018 | Scottish and Southern Energy (SSE) |
| Dorenell Wind Farm (Previously Site A and B Scaut Hill) | 177 MW | 59 | Grampian, Scotland | 2018 | EDF Energy Renewables/ Infinergy |
| Clyde Wind Farm Extension (Clyde 2) | 172.8 MW | 54 | Strathclyde, Scotland | 2017 | Scottish and Southern Energy (SSE)/ GIB |
| Griffin Wind farm | 156 MW | 52 | Tayside, Scotland | 2012 | Greenpower (Griffin) Ltd |
| Fallago Rig | 144 MW | 48 | Borders, Scotland | 2013 | EDF Energy Renewables |
| Crystal Rig Wind Farm Phase 2a | 138 MW | 60 | Borders, Scotland | 2010 | Fred Olsen Renewables |
| Harestanes | 136 MW | 68 | Dumfries and Galloway, Scotland | 2014 | Scottish Power Renewables |
| Black Law | 124 MW | 54 | Strathclyde, Scotland | 2004 | Scottish Power Renewables |
| Arecleoch Windfarm | 120 MW | 60 | Ayrshire, Scotland | 2011 | Scottish Power Renewables |
| Hadyard Hill | 120 MW | 52 | Strathclyde, Scotland | 2006 | Scottish and Southern Energy (SSE) |
| Bhlaraidh (previously Balmacaan) | 110 MW | 32 | Highland, Scotland | 2017 | Scottish and Southern Energy (SSE) |
| Whitelee Windfarm Extension phase 2 | 109 MW | 36 | Strathclyde, Scotland | 2013 | Scottish Power |
| Whitelee Windfarm Extension Phase 1 | 108 MW | 36 | Strathclyde, Scotland | 2012 | Scottish Power Renewables |
| Dunmaglass Wind Farm | 94 MW | 33 | Highland, Scotland | 2016 | Scottish and Southern Energy (SSE) |
| Creag Riabhach Wind Farm | 92.4 MW | 22 | Highland, Scotland | 2023 | ERG |
| Farr Wind Farm | 92 MW | 40 | Highland, Scotland | 2005 | Innogy (formerly RWE npower) |
| Brochloch Rig (formerly Windy Standard II) | 90 MW | 30 | Dumfries and Galloway, Scotland | 2017 | Fred Olsen Renewables |
| Kype Muir Wind Farm | 88.4 MW | 26 | Strathclyde, Scotland | 2019 | Banks Renewables |
| Beinneun | 85 MW | 25 | Highland, Scotland | 2017 | Octopus Investments/Blue Energy |
| Hagshaw Hill (Repowering) | 84 MW | 14 | Lanarkshire, Scotland | 2025 | Scottish Power Renewables |
| Aikengall IIa Community Wind Farm | 81.7 MW | 19 | Borders, Scotland | 2021 | Community Windpower |
| Sandy Knowe Wind Farm | 81.6 MW | 24 | Dumfries and Galloway, Scotland | 2023 | ERG |
| Limekiln Wind Farm | 79.8 MW | 19 | Highland, Scotland | 2025 | Boralex/Infinergy |
| Braes O'Doune | 72 MW | 36 | Stirling, Scotland | 2006 | Greencoat UK Wind |
| Enoch Hill | 70 MW | 15 | Strathclyde, Scotland | 2026 | E.ON Renewables |
| Gordonbush | 70 MW | 35 | Highland, Scotland | 2012 | Scottish and Southern Energy (SSE) |
| Corriegarth | 69.5 MW | 23 | Highland, Scotland | 2016 | Greencoat Capital |
| Dersalloch | 69 MW | 23 | Strathclyde, Scotland | 2016 | Scottish Power Renewables |
| Strathy North | 67.7 MW | 33 | Highland, Scotland | 2015 | Scottish and Southern Energy (SSE) |
| Kype Muir Wind Farm Extension | 67.2 MW | 15 | Strathclyde, Scotland | 2024 | Banks Renewables |
| Benbrack Wind Farm | 67.1 MW | 15 | East Ayrshire, Scotland | 2025 | E.ON Renewables / Red Rock Power Limited |
| Berry Burn | 66.7 MW | 29 | Grampian, Scotland | 2014 | Statkraft |
| Galawhistle | 66 MW | 22 | Strathclyde, Scotland | 2017 | Ventient (formerly Infinis) |
| Moy Wind Farm (2nd Application) | 66 MW | 20 | Highland, Scotland | 2016 | Eneco |
| Paul's Hill and Extension | 65 MW | 28 | Grampian, Scotland | 2006 | Fred Olsen Renewables |
| Crystal Rig Phase 1 | 62.5 MW | 25 | Borders, Scotland | 2004 | Fred Olsen Renewables |
| Aikengall II, Wester Dod Community Wind Farm | 60.8 MW | 19 | Lothian, Scotland | 2017 | Community Windpower |
| Mid Hill I | 57.5 MW | 25 | Grampian, Scotland | 2013 | Fred Olsen Renewables |
| Mark Hill | 56 MW | 24 | Strathclyde, Scotland | 2011 | Force 9 Energy |
| Corriemoillie | 54.4 MW | 17 | Highland, Scotland | 2017 | EDF Energy Renewables |
| Blackcraig | 52.9 MW | 23 | Dumfries and Galloway, Scotland | 2018 | Blue Energy |
| Baillie Wind Farm | 52.5 MW | 21 | Highland, Scotland | 2013 | Baillie Windfarm Ltd |
| Harburnhead Wind Farm | 51.7 MW | 22 | Lothian, Scotland | 2016 | Gresham House |
| Lochluichart | 51 MW | 17 | Highland, Scotland | 2014 | Eneco |
| Middle Muir Wind Farm | 51 MW | 15 | Strathclyde, Scotland | 2019 | Banks Renewables |
| Rothes Wind (Cairn Uish) | 50.6 MW | 22 | Grampian, Scotland | 2004 | Natural Power Consultants |
| Afton Wind Farm | 50 MW | 25 | Strathclyde, Scotland | 2018 | InfraRed Capital Partners/ E.on |
| Camster | 50 MW | 25 | Highland, Scotland | 2013 | E.ON UK |
| Glen Kyllachy Wind Farm | 48.5 MW | 20 | Highland, Scotland | 2022 | Greencoat UK Wind |
| Black Law Extension - 1a | 48.4 MW | 29 | Strathclyde, Scotland | 2016 | Scottish Power Renewables |
| A'Chruach (Phase 1) | 48.3 MW | 21 | Strathclyde, Scotland | 2016 | Infinis (formerly Novera Energy) |
| Causeymire | 48.3 MW | 24 | Highland, Scotland | 2004 | Innogy (formerly RWE npower) |
| Aikengall | 48 MW | 16 | Lothian, Scotland | 2008 | Community Wind Power |
| Broken Cross (Former Surface Mine) | 48 MW | 10 | Lanarkshire, Scotland | 2024 | BayWa r.e. UK Limited |
| Crossdykes | 48 MW | 10 | Dumfries and Galloway, Scotland | 2021 | Muirhall Energy |
| Cumberhead Wind Farm | 48 MW | 12 | Lanarkshire, Scotland | 2023 | Octopus Renewables Infrastructure Trust |
| Hill of Towie (Drummuir) | 48 MW | 21 | Grampian, Scotland | 2012 | Renewable Energy Systems (RES) |
| Kilbraur Windfarm | 47.5 MW | 19 | Highland, Scotland | 2008 | Renewable Development Company (RDC) |
| Gordonbush (extension) | 47 MW | 11 | Highland, Scotland | 2021 | Scottish and Southern Energy (SSE) |
| Carraig Gheal | 46 MW | 20 | Strathclyde, Scotland | 2013 | Green Power |
| Douglas West and Dalquhandy Renewable Energy Project | 45 MW | 13 | Lanarkshire, Scotland | 2023 | Greencoat (formerly 3R Energy/Blue Energy) / BayWa r.e |
| Beinn an Tuirc Phase 2 | 43.7 MW | 19 | Strathclyde, Scotland | 2014 | Scottish Power Renewables |
| Fairburn | 43 MW | 20 | Highland, Scotland | 2010 | Scottish and Southern Energy (SSE) |
| Windy Rig Wind Farm | 43 MW | 12 | Dumfries and Galloway, Scotland | 2021 | Statkraft UK |
| Dalquhandy Windfarm | 42 MW | 10 | Strathclyde, Scotland | 2023 | Dalquhandy Wind Farm Limited |
| Edinbane Wind Farm | 41.4 MW | 18 | Highland, Scotland | 2010 | Vattenfall |
| Rothes Wind Farm (Extension) (II) | 41.4 MW | 18 | Grampian, Scotland | 2013 | Fred Olsen Renewables |
| Millennium Windfarm | 40 MW | 16 | Highland, Scotland | 2008 | Renewable Development Company (RDC) Scotland (Ltd) for FALCK RENEWABLES |
| Tom Nan Clach | 39 MW | 13 | Highland, Scotland | 2019 | Infinergy |
| Achany Wind Farm | 38 MW | 19 | Highland, Scotland | 2010 | Scottish and Southern Energy (SSE) |
| Longpark | 38 MW | 19 | Borders, Scotland | 2009 | Wind Prospect |
| Earlsburn | 37.5 MW | 14 | Stirling, Scotland | 2007 | Falck Renewables |
| Clashindarroch | 37 MW | 18 | Grampian, Scotland | 2015 | Vattenfall |
| Drumderg | 36.8 MW | 16 | Tayside, Scotland | 2008 | Scottish and Southern Energy (SSE) |
| Ewe Hill (extension) | 36.8 MW | 16 | Dumfries and Galloway, Scotland | 2017 | Scottish Power Renewables |
| Minsca | 36.8 MW | 16 | Dumfries and Galloway, Scotland | 2008 | Airtricity |
| Novar Wind Farm (Extension) | 36.8 MW | 16 | Highland, Scotland | 2012 | RWE npower |
| Andershaw | 36 MW | 14 | Strathclyde, Scotland | 2016 | Statkraft UK |
| Auchrobert Wind Farm | 36 MW | 12 | Strathclyde, Scotland | 2017 | Falck Renewables |
| Camster II | 36 MW | 10 | Highland, Scotland | 2026 | E.ON UK |
| Airies Farm | 35 MW | 14 | Dumfries and Galloway, Scotland | 2017 | NTR |
| Blary Hill Wind Farm | 35 MW | 14 | Strathclyde, Scotland | 2022 | Renewables Infrastructure Group / Renewable Energy Systems (RES) |
| Halsary Wind Farm | 34 MW | 15 | Highland, Scotland | 2021 | Scottish Power Renewables |
| Pines Burn Wind Farm | 33.6 MW | 7 | Scottish Borders, Scotland | 2024 | EnergieKontor UK |
| Cruach Mhor | 33.3 MW | 35 | Strathclyde, Scotland | 2004 | Scottish Power Renewables |
| Sanquhar Community Windfarm | 32.4 MW | 9 | Dumfries and Galloway, Scotland | 2018 | Community Windpower |
| Calliachar | 32.2 MW | 14 | Tayside, Scotland | 2013 | Scottish and Southern Energy (SSE) |
| Bowbeat Emly Bank / Rough Side | 31.2 MW | 24 | Borders, Scotland | 2002 | PowerGen and Natural Power |
| Tormywheel | 30.8 MW | 15 | Lothian, Scotland | 2017 | BlackRock (formerly Muirhall Energy) |
| Dalswinton | 30 MW | 15 | Dumfries and Galloway, Scotland | 2008 | Airtricity Scotland |
| Solwaybank Wind Farm | 30 MW | 15 | Dumfries and Galloway, Scotland | 2020 | The Renewables Infrastructure Group (TRIG) |
| West Browncastle | 30 MW | 12 | Strathclyde, Scotland | 2014 | Falck Renewables |
| Coire Na Cloiche Wind Farm | 29.9 MW | 13 | Highland, Scotland | 2020 | RockbySea |
| Dungavel Hill | 29.9 MW | 13 | Strathclyde, Scotland | 2015 | John Laing Environmental Assets Group |
| Hill of Stroupster Windfarm | 29.9 MW | 12 | Highland, Scotland | 2015 | Greencoat UK Wind |
| Quixwood Moor | 29.9 MW | 13 | Borders, Scotland | 2017 | NTR PLC |
| Beinn Tharsuinn Windfarm Project | 29.8 MW | 17 | Highland, Scotland | 2005 | CRE Energy/ Scottish Power |
| Dun Law Extension | 29.8 MW | 35 | Borders, Scotland | 2009 | Renewable Energy Systems (RES) |
| Hare Hill Extension | 29.8 MW | 35 | Strathclyde, Scotland | 2016 | Scottish Power Renewables |
| Beinn an Tuirc | 29.7 MW | 45 | Strathclyde, Scotland | 2001 | CRE Energy/ Scottish Power |
| Penmanshiel Wind Farm | 28.7 MW | 14 | Borders, Scotland | 2016 | Renewable Energy Systems (RES) |
| Black Hill (Borders) | 28.6 MW | 22 | Borders, Scotland | 2007 | Renewable Energy Systems (RES) |
| Drone Hill | 28.6 MW | 22 | Borders, Scotland | 2012 | Greencoat UK Wind |
| Calder Water Community Wind Farm | 28 MW | 14 | Strathclyde, Scotland | 2013 | Community Windpower (Community Wind Power) |
| Kelburn | 28 MW | 14 | Strathclyde, Scotland | 2012 | Renewable Energy Systems (RES) |
| Hill of Glaschyle Wind Farm | 27.6 MW | 12 | Grampian, Scotland | 2016 | Muirden Energy |
| Toddleburn | 27.6 MW | 12 | Borders, Scotland | 2010 | Scottish and Southern Energy (SSE) |
| Glenchamber Wind Farm | 27.5 MW | 11 | Dumfries and Galloway, Scotland | 2016 | Renewable Energy Systems (RES) |
| West Benhar wind farm | 27.2 MW | 8 | Strathclyde, Scotland | 2023 | EDF Energy Renewables |
| Green Knowes | 27 MW | 18 | Tayside, Scotland | 2008 | CRE Energy/ Scottish Power |
| Bad a Cheo Wind Farm | 26.7 MW | 13 | Highland, Scotland | 2019 | Innogy |
| Burnfoot Hill | 26 MW | 13 | Clackmannanshire, Scotland | 2010 | EDF Energies Nouvelles |
| Burnhead | 26 MW | 13 | Stirling, Scotland | 2016 | Wind Prospect Developments/ EDF |
| Glens of Foudland | 26 MW | 20 | Grampian, Scotland | 2005 | Green Investment Bank (Blackrock) |
| Hagshaw Hill Wind Farm Extension | 26 MW | 20 | Strathclyde, Scotland | 2008 | Scottish Power Renewables |
| Whiteside Hill | 25.3 MW | 11 | Dumfries and Galloway, Scotland | 2018 | Whiteside Hill Farm (Scotland) |
| Assel Valley Wind Farm | 25 MW | 11 | Strathclyde, Scotland | 2016 | Falck Renewables |
| Easter Tulloch Wind Farm (Tullo Extension) | 25 MW | 10 | Grampian, Scotland | 2014 | N R Gammie Partnership |
| Little Raith Farm | 25 MW | 9 | Fife, Scotland | 2012 | Renewables Infrastructure Group |
| Minnygap | 25 MW | 10 | Dumfries and Galloway, Scotland | 2017 | Minnygap (formerly RES) |
| Rosehall Hill Forest Windfarm | 24.7 MW | 19 | Highland, Scotland | 2013 | E.ON UK |
| Ardrossan | 24 MW | 12 | Strathclyde, Scotland | 2003 | Airtricity |
| Greengairs East Wind Farm | 24 MW | 8 | Strathclyde, Scotland | 2023 | Muirhall Energy |
| Inverclyde Wind Farm (Corlic Hill) | 24 MW | 8 | Strathclyde, Scotland | 2021 | BayWa r.e. (formerly Forsa) |
| Beinneun Windfarm Extension | 23.8 MW | 7 | Highland, Scotland | 2017 | Octopus Investments/Blue Energy |
| Ben Aketil | 23 MW | 10 | Highland, Scotland | 2007 | RDC Scotland (Renewable Development Co.) |
| Burn of Whilk | 22.5 MW | 9 | Highland, Scotland | 2015 | RWE npower |
| Earlsburn North (Kingsburn) Wind Farm | 22.5 MW | 9 | Stirling, Scotland | 2016 | Falck Renewables |
| Freasdail Wind Farm | 22.5 MW | 11 | Strathclyde, Scotland | 2017 | The Renewables Infrastructure Group (TRIG) |
| Glen App | 22 MW | 11 | Strathclyde, Scotland | 2017 | Scottish Power Renewables |
| Glenkerie Wind Farm | 22 MW | 11 | Borders, Scotland | 2012 | Novera Energy |
| North Rhins | 22 MW | 11 | Dumfries and Galloway, Scotland | 2010 | Greencoat UK Wind |
| Brochloch Rig 1 (formerly Windy Standard) | 21.6 MW | 36 | Dumfries and Galloway, Scotland | 1996 | Fred Olsen Renewables |
| Limekiln Wind Farm (Extension) | 21 MW | 5 | Highland, Scotland | 2025 | Infinergy / Boralex |
| Crystal Rig Extension II | 20.7 MW | 9 | Borders, Scotland | 2010 | Natural Power Consultants |
| Cour Wind Farm | 20.5 MW | 10 | Strathclyde, Scotland | 2016 | Octopus Investments/Blue Energy |
| Craigengelt | 20 MW | 8 | Stirling, Scotland | 2010 | Scotia Wind Ltd |
| Kilbraur Windfarm Farlary - Extension | 20 MW | 8 | Highland, Scotland | 2011 | Falck Renewables |
| Tralorg Wind Farm | 20 MW | 8 | Strathclyde, Scotland | 2020 | RPMI Railpen (formerly BayWa) |
| Artfield Fell | 19.5 MW | 15 | Dumfries and Galloway, Scotland | 2005 | Scottish and Southern Energy (SSE) |
| An Suidhe | 19.3 MW | 23 | Strathclyde, Scotland | 2010 | RWE npower |
| Pearie Law Wind Farm | 19.2 MW | 6 | Lothian, Scotland | 2016 | EDF Energy Renewables |
| Kirk Hill Wind Farm | 18.8 MW | 8 | Ayrshire, Scotland | 2024 | Corolis Energy/ ESB / Ripple Energy |
| Wathegar 2 Wind Farm | 18.5 MW | 9 | Highland, Scotland | 2017 | BayWa r.e. |
| Earlseat | 18.4 MW | 8 | Fife, Scotland | 2014 | The Renewables Infrastructure Group (TRIG) |
| Kildrummy Windfarm | 18.4 MW | 8 | Grampian, Scotland | 2013 | Greencoat UK Wind/Bay Wa .r.e/ SunGift |
| Mid Hill - Phase II | 18.4 MW | 8 | Grampian, Scotland | 2014 | Fred Olsen Renewables |
| Wether Hill | 18.2 MW | 14 | Dumfries and Galloway, Scotland | 2007 | Scottish Power/CRE Energy |
| Edintore Wind Farm | 18 MW | 6 | Grampian, Scotland | 2016 | Vento Ludens |
| Lochluichart (Extension) | 18 MW | 6 | Highland, Scotland | 2014 | Infinergy |
| Millour Hill Community Windfarm | 18 MW | 6 | Strathclyde, Scotland | 2012 | Community Windpower |
| Wardlaw Wood | 18 MW | 6 | Strathclyde, Scotland | 2006 | Wind Prospect / Community Windpower |
| Tullo Farm | 17.5 MW | 7 | Grampian, Scotland | 2010 | West Coast Energy (agents for Tullo Wind Ltd and GE Wind) |
| Dun Law | 17.2 MW | 26 | Borders, Scotland | 2000 | Renewable Energy Systems (RES) |
| Meall an Tuirc Wind Farm | 17 MW | 34 | Highland, Scotland | 1997 | RWE npower |
| Boyndie Airfield | 16.7 MW | 8 | Grampian, Scotland | 2006 | RDC Scotland Ltd/ Falck Renewables |
| Howpark Wind Farm | 16 MW | 8 | Scottish Borders, Scotland | 2024 | Eurowind (UK) Limited |
| Langhope Rig | 16 MW | 10 | Borders, Scotland | 2015 | Greencoat UK Wind |
| Deucheran Hill | 15.8 MW | 9 | Strathclyde, Scotland | 2001 | Powergen Renewables |
| Carscreugh Renewable Energy Park | 15.3 MW | 18 | Dumfries and Galloway, Scotland | 2014 | John Laing Environmental Assets Group/ REG Power Management |
| Black Law Extension - 1b | 15 MW | 5 | Strathclyde, Scotland | 2016 | Scottish Power Renewables |
| Clachan Flats Wind Farm | 15 MW | 9 | Strathclyde, Scotland | 2008 | AMEC/ Border Winds |
| Cnoc Donn Arnicle | 15 MW | 26 | Strathclyde, Scotland | 2001 | CRE Energy/ Scottish Power |
| Millennium Extension II | 15 MW | 6 | Highland, Scotland | 2011 | West Coast Energy Ltd/Falck Renewables |
| Nutberry Wind Farm | 15 MW | 6 | Strathclyde, Scotland | 2013 | Renantis Falck Renewables Limited |
| Tullymurdoch Wind Farm | 14.4 MW | 7 | Tayside, Scotland | 2018 | Temporis Capital |
| Bankend Rig | 14.3 MW | 11 | Strathclyde, Scotland | 2013 | I & H Brown Ltd |
| Pates Hill | 14 MW | 7 | Lothian, Scotland | 2010 | Your Energy |
| Crystal Rig Wind Farm Phase III | 13.8 MW | 6 | Borders, Scotland | 2016 | Fred Olsen Renewables |
| Ewe Hill | 13.8 MW | 6 | Dumfries and Galloway, Scotland | 2016 | Scottish Power Renewables |
| Pentland Road Wind Farm | 13.8 MW | 6 | Western Isles, Scotland | 2013 | Arnish Electric Ltd / Farm Energy Ltd |
| Hare Hill (East Ayrshire) | 13.2 MW | 20 | Strathclyde, Scotland | 2000 | Scottish Power Renewables |
| Boulfruich | 13 MW | 15 | Highland, Scotland | 2005 | Private Developer |
| Tangy Wind Farm/Tangy 1 | 12.8 MW | 15 | Strathclyde, Scotland | 2002 | Border Wind / Scottish and Southern (SSE) |
| Gordonstown Hill Wind Farm | 12.5 MW | 5 | Grampian, Scotland | 2013 | Ventient (formerly Infinis) |
| Dummuie | 12.3 MW | 7 | Grampian, Scotland | 2007 | Tetro Energy Ltd (ECO2) |
| Muirhall | 12.3 MW | 6 | Strathclyde, Scotland | 2011 | Lomond Energy |
| Methlick Farmers Wind Energy Project | 12 MW | 6 | Grampian, Scotland | 2011 | Orkney Sustainable Energy |
| Middleton Wind Farm | 12 MW | 6 | Strathclyde, Scotland | 2013 | Scottish Power Renewables |
| Rhodders Wind Farm | 12 MW | 6 | Clackmannanshire, Scotland | 2016 | EDF/Wind Prospect |
| Tod Hill Farm Wind Turbines | 12 MW | 4 | Falkirk, Scotland | 2015 | Falkirk Tod Hill Wind Limited |
| Allt Dearg Wind Farmers LLP | 10.8 MW | 12 | Strathclyde, Scotland | 2012 | Ormsary and Stronachullin Estates (Allt Dearg Wind Farmers LLP) |
| Burnfoot East Wind Farm (further extension) | 10.8 MW | 3 | Clackmannanshire, Scotland | 2020 | Wind Prospect Developments |
| Achlachan Wind Farm | 10 MW | 5 | Highland, Scotland | 2019 | Whirlwind Renewables |
| Binn Eco Park - Wind Farm | 10 MW | 4 | Perth and Kinross, Scotland | 2020 | Binn Eco Park |
| Cairnborrow | 10 MW | 5 | Grampian, Scotland | 2017 | Engie (GDF Suez) |
| Craig Wind Farm | 10 MW | 4 | Dumfries and Galloway, Scotland | 2007 | Craig Wind Farm Co |
| Glenurquhart and Strathglass Wind Farm project | 10 MW | 5 | Highland, Scotland | 2013 | Corrimony Energy Ltd & Soirbheas |
| Meikle Carewe | 10 MW | 12 | Grampian, Scotland | 2013 | The Renewables Infrastructure Group (TRIG) |
| Millennium Extension | 10 MW | 4 | Highland, Scotland | 2008 | West Coast Energy /Falck Renewables |
| Spurness Wind Farm Repowering | 10 MW | 5 | Orkney Islands, Scotland | 2012 | Scottish and Southern Energy (SSE) |
| Tullo Wind Farm South (Ext.) | 10 MW | 4 | Grampian, Scotland | 2014 | Eneco |
| Wathegar wind farm | 10 MW | 5 | Highland, Scotland | 2013 | Private Developer |
| Westfield | 10 MW | 4 | Fife, Scotland | 2013 | Ventient (formerly Infinis) |
| Hill of Tillymorgan (Kirkton Farm) Wind turbines | 9.6 MW | 3 | Grampian, Scotland | 2016 | LocoGen/ Green Cat Renewables |
| Lochelbank Wind Farm II | 9.6 MW | 12 | Tayside, Scotland | 2011 | RWE npower |
| Land at Overside and Greenwellheads Farms | 9.2 MW | 4 | Grampian, Scotland | 2013 | Greenside Wind Energy Ltd |
| Lochend Wind Farm | 9.2 MW | 4 | Highland, Scotland | 2017 | Wind Harvest |
| NEILSTON WIND FARM | 9.2 MW | 4 | Strathclyde, Scotland | 2013 | Renewables Infrastructure Group |
| Welton Of Creuchies | 9.2 MW | 4 | Tayside, Scotland | 2018 | Green Cat Renewables |
| Balmurrie Fell Wind Farm | 9.1 MW | 7 | Dumfries and Galloway, Scotland | 2012 | Scottish Southern Energy |
| Bendealt Wind Farm, Highland | 9 MW | 18 | Highland, Scotland | 1997 | RWE npower |
| Blantyre Muir Wind Farm | 9 MW | 3 | Strathclyde, Scotland | 2013 | Blantyre Muir Wind Energy Ltd� |
| Point Wind / Beinn Ghrideag Farm | 9 MW | 3 | Western Isles, Scotland | 2015 | Point Power & Energy Ltd / SgurrEnergy |
| Torrance Farm | 9 MW | 3 | Strathclyde, Scotland | 2013 | Future Spectrum Ltd |
| Drumduff | 8.5 MW | 3 | Lothian, Scotland | 2017 | Green Breeze Energy Ltd |
| Watsonhead Wind Farm | 8.4 MW | 2 | Lanarkshire, Scotland | 2023 | Green Cat Renewables |
| Muirhall South | 8.3 MW | 3 | Strathclyde, Scotland | 2016 | Muirhall Energy |
| Barlockhart Moor | 8.1 MW | 4 | Dumfries and Galloway, Scotland | 2013 | West Coast Energy |
| Beinn Ghlas Wind Farm | 7.8 MW | 14 | Strathclyde, Scotland | 1999 | RWE npower |
| Hagshaw Hill Wind Farm | 7.8 MW | 13 | Strathclyde, Scotland | 1995 | Trigen |
| Hagshaw Hill Wind Farm | 7.8 MW | 13 | Strathclyde, Scotland | 1995 | Trigen |
| St John Hill | 7.7 MW | 3 | Grampian, Scotland | 2013 | Auquhirie Land Company Ltd |
| St. Johns Hill | 7.7 MW | 9 | Grampian, Scotland | 2013 | K E Projects AF |
| Blantyre Muir Wind Farm extension | 7.5 MW | 3 | Strathclyde, Scotland | 2014 | West Coast Energy |
| BROWNIELEYS - 3 WIND TURBINES | 7.5 MW | 3 | Grampian, Scotland | 2017 | Brownieleys Renewables/Muirden Energy |
| GlaxoSmithKline Wind Project | 7.5 MW | 3 | Strathclyde, Scotland | 2013 | Glaxosmithkline |
| Lairg Wind Farm | 7.5 MW | 3 | Highland, Scotland | 2012 | ABO Wind |
| Tullo Wind Farm North Extension (Shiels Wind Farm) | 7.5 MW | 3 | Grampian, Scotland | 2014 | Eneco |
| Ardoch and Over Enoch Wind Farm (Ardoch) | 7.2 MW | 3 | Strathclyde, Scotland | 2014 | 2020 Renewables/ NTR |
| Auchadaduie Wind Farm | 6.9 MW | 3 | Strathclyde, Scotland | 2018 | Fyne Futures |
| Clentrie Wind Farm (Gevens) | 6.9 MW | 3 | Fife, Scotland | 2016 | Rev Ltd |
| Deuchries | 6.9 MW | 3 | Grampian, Scotland | 2017 | Force 9 Energy / Catamount Energy/ Green Cat |
| Hill of Fiddes | 6.9 MW | 3 | Grampian, Scotland | 2010 | Infinis, previously Broadview Energy |
| Hill of Skilmafilly Cloffrickford (Denmore) Wind Farm | 6.9 MW | 3 | Grampian, Scotland | 2015 | SAC Environment And Design |
| Hillhead of Auquhirie | 6.9 MW | 3 | Grampian, Scotland | 2013 | Octopus Investements/Blue Energy (previously Auquhirie Land Company Ltd) |
| Hoprigshiels Community Wind Farm | 6.9 MW | 3 | Borders, Scotland | 2017 | Private Developer |
| Lochcarnan Community Windfarm | 6.9 MW | 3 | Western Isles, Scotland | 2013 | Storas Uibhist |
| Shielburn Farm | 6.9 MW | 3 | Grampian, Scotland | 2013 | Green Cat Renewables |
| Jacksbank Wind Farm (Glenbervie) | 6.8 MW | 3 | Grampian, Scotland | 2014 | East Coast Viners |
| Muirhall Extension | 6.8 MW | 2 | Strathclyde, Scotland | 2014 | Muirhall Energy |
| Ark Hill | 6.4 MW | 8 | Tayside, Scotland | 2013 | Green Cat Renewables |
| Middle Balbeggie Wind Turbines | 6.4 MW | 2 | Fife, Scotland | 2016 | Capital Dynamics |
| Millour Hill Community Windfarm (Extension) | 6.4 MW | 2 | Strathclyde, Scotland | 2016 | Community Windpower |
| Achairn | 6.2 MW | 3 | Highland, Scotland | 2009 | Messrs James and Ronald Innes |
| Ardrossan Extension | 6 MW | 3 | Strathclyde, Scotland | 2008 | Airtricity |
| Carcant Windfarm | 6 MW | 3 | Borders, Scotland | 2010 | Greencoat UK Wind |
| Lochhead Farm | 6 MW | 3 | Strathclyde, Scotland | 2009 | A7 Energy / Green Energy |
| Srondoire Community Wind Farm | 6 MW | 3 | Strathclyde, Scotland | 2015 | Srondoire Wind Farmers LLP |
| St Fergus Moss Wind Farm | 6 MW | 3 | Grampian, Scotland | 2012 | Greenspan Electric St Fergus Ltd |
| Tangy Wind Farm Extension/Tangy 2 | 6 MW | 7 | Strathclyde, Scotland | 2011 | Scottish and Southern Energy (SSE) |
| Torrance Farm Wind Park Extension | 5.7 MW | 2 | Strathclyde, Scotland | 2015 | Capital Dynamics |
| Clochnahill Wind Farm | 5.2 MW | 4 | Grampian, Scotland | 2012 | Private Developer |
| Forss Wind Farm (Extension) | 5.2 MW | 4 | Highland, Scotland | 2007 | Renewable Energy Systems (RES) |
| Pogbie Wind Farm 1 | 5.1 MW | 6 | Lothian, Scotland | 2019 | Mongoose (formerly Energy Law Unlimited) |
| Burgar Hill | 5 MW | 2 | Orkney Islands, Scotland | 2006 | Orkney Sustainable Energy |
| House O'Hill | 5 MW | 3 | Grampian, Scotland | 2010 | Green Cat Renewables |
| Kinegar Quarry | 5 MW | 2 | Borders, Scotland | 2017 | Airvolution Energy |
| Phase 1 Bettyhill Wind Farm | 5 MW | 2 | Highland, Scotland | 2013 | North British Windpower Ltd |
| Hill of Lybster | 4.9 MW | 4 | Highland, Scotland | 2003 | Fivestone Ltd (subsidiary of Abbey Produce) |
| Pogbie Wind Farm 2 | 4.8 MW | 6 | East Lothian, Scotland | 2019 | Mongoose (formerly Energy Law Unlimited/ Pogbie Windfarm) |
| Deuchries Windfarm (extension) (Bradley 2) | 4.7 MW | 2 | Aberdeenshire, Scotland | 2024 | Blackfinch Energy |
| National Wind Turbine Test Site | 4.7 MW | 2 | Strathclyde, Scotland | 2001 | NEL |
| Backhill of Yonderton Wind Cluster | 4.6 MW | 2 | Grampian, Scotland | 2014 | Private Developer |
| Beinn Tharsuinn Extension (Beinn nan Oighrean) | 4.6 MW | 2 | Highland, Scotland | 2009 | Midefearn Renewables |
| Ben Aketil Extension | 4.6 MW | 2 | Highland, Scotland | 2011 | Ben Aketil Wind Energy Ltd |
| Brotherton (formerly Paul Matthew Hill wind turbines) | 4.6 MW | 2 | Grampian, Scotland | 2017 | Renewable Energy Ventures |
| Droop Hill Wind Farm x | 4.6 MW | 2 | Grampian, Scotland | 2014 | Macphie Of Glenbervie Ltd |
| Greenhill Croft | 4.6 MW | 2 | Grampian, Scotland | 2012 | Green Cat Renewables |
| Haddo | 4.6 MW | 2 | Grampian, Scotland | 2011 | Private Developer |
| Milton of Fisherie Wind Cluster | 4.6 MW | 2 | Grampian, Scotland | 2016 | LocoGen |
| Mossmorran Wind Farm | 4.6 MW | 2 | Fife, Scotland | 2015 | Airvolution Energy |
| Muirake | 4.6 MW | 2 | Grampian, Scotland | 2011 | Vento Ludens |
| Netherton of Windyhills | 4.6 MW | 2 | Grampian, Scotland | 2014 | Strathdee Energy |
| Strath of Brydock | 4.6 MW | 2 | Grampian, Scotland | 2009 | Green Cat Renewables |
| Keith Hill | 4.5 MW | 5 | Lothian, Scotland | 2017 | Sky Wind Energy |
| Little Byth | 4.5 MW | 3 | Grampian, Scotland | 2012 | Lovie Ltd |
| North Yell Wind Farm (Garth Community Wind Farm) | 4.5 MW | 5 | Shetland, Scotland | 2017 | Garth Wind (North Yell Development Council) |
| Ardoch and Over Enoch Wind Farm (Over Enoch) | 4.3 MW | 2 | Strathclyde, Scotland | 2014 | 2020 Renewables/ NTR |
| Hammar's Hill | 4.3 MW | 5 | Orkney Islands, Scotland | 2010 | Hammers Hill Energy Ltd |
| Burnfoot Hill Extension | 4 MW | 2 | Tayside, Scotland | 2014 | Private Developer |
| Greendykeside | 4 MW | 2 | Strathclyde, Scotland | 2007 | A7 Energy |
| Michelin Tyre Co Ltd - Dundee | 4 MW | 2 | Tayside, Scotland | 2006 | Ecotricity |
| Arnish Moor | 3.9 MW | 3 | Western Isles, Scotland | 2006 | Arnish Electric Ltd / Farm Energy |
| Bilbster Wind Farm | 3.9 MW | 3 | Highland, Scotland | 2008 | Private Developer |
| Burradale Hill | 3.7 MW | 5 | Shetland, Scotland | 2000 | Shetland Aerogenerators |
| Skelmonae Wind Farm | 3.2 MW | 4 | Grampian, Scotland | 2009 | Private Developer |
| St Johns Wells Wind Cluster Extension | 3.2 MW | 4 | Grampian, Scotland | 2015 | Green Cat Renewables |
| Cathkin Braes Wind Farm (Castlemilk) | 3 MW | 1 | Strathclyde, Scotland | 2013 | Scottish and Southern Energy (SSE) |
| Gremista Wind Farm | 3 MW | 1 | Shetland, Scotland | 2015 | Shetland Aerogenerators |
| Bu Farm | 2.7 MW | 3 | Orkney Islands, Scotland | 2002 | Longearth Ltd/ Farm Energy |
| Loch Sminig Wind Project | 2.7 MW | 3 | Western Isles, Scotland | 2015 | Urras Oighreachd Ghabhsainn |
| Rothiesholm | 2.7 MW | 3 | Orkney Islands, Scotland | 2002 | Longearth Ltd / Farm Energy |
| Cairnmore Farm | 2.6 MW | 3 | Grampian, Scotland | 2010 | Private Developer |
| Forss Wind Farm | 2.6 MW | 2 | Highland, Scotland | 2003 | Renewable Energy Systems (RES) |
| Woodlands Wind Farm | 2.6 MW | 3 | Lanarkshire, Scotland | 2016 | WhiteRock Energy |
| Craig Wind Farm (Extension) | 2.5 MW | 1 | Dumfries and Galloway, Scotland | 2017 | Temporis Capital |
| Damhead Farm | 2.5 MW | 1 | Strathclyde, Scotland | 2013 | Private Developer |
| GlaxoSmithKline Wind Project (Turbine 4) | 2.5 MW | 1 | Strathclyde, Scotland | 2014 | GlaxoSmithKline |
| Hill of Easterton | 2.5 MW | 1 | Grampian, Scotland | 2005 | Mackies |
| Auchinderran Wind Farm | 2.4 MW | 3 | Grampian, Scotland | 2014 | Green Cat Renewables |
| Brockholes Wind Cluster | 2.4 MW | 3 | Borders, Scotland | 2013 | Brockholes Farm |
| Castle of Auchry Farm | 2.4 MW | 3 | Grampian, Scotland | 2013 | Green Cat Renewables |
| Gawnsmoss Cluster | 2.4 MW | 3 | Aberdeenshire, Scotland | 2017 | Farm Energy Consulting |
| LADEHEAD FARM - WIND TURBINES | 2.4 MW | 3 | Strathclyde, Scotland | 2016 | PI Renewables 2 Ltd |
| Mains of Hatton | 2.4 MW | 3 | Grampian, Scotland | 2012 | Eco2 /GreenCAT |
| Plascow wind cluster | 2.4 MW | 3 | Dumfries and Galloway, Scotland | 2015 | Private Developer |
| Rosehill Wind Turbines | 2.4 MW | 3 | Stirling, Scotland | 2015 | Green Cat Renewables |
| St John's Well | 2.4 MW | 3 | Grampian, Scotland | 2009 | Green Cat Renewables |
| Upper Ardgrain Wind Farm | 2.4 MW | 3 | Grampian, Scotland | 2010 | Green Cat Renewables |
| West Knock Wind Cluster | 2.4 MW | 3 | Grampian, Scotland | 2011 | West Knock Farm |
| Bogenlea Farm | 2.3 MW | 1 | Grampian, Scotland | 2014 | Eco2 |
| Boyndie Airfield Extension | 2.3 MW | 1 | Grampian, Scotland | 2010 | Boyndie Wind Farm |
| Burgar Hill (land Near), Evie | 2.3 MW | 1 | Orkney Islands, Scotland | 2009 | Unknown |
| Courtstone Wind Turbine | 2.3 MW | 1 | Grampian, Scotland | 2009 | Private Developer |
| Denhill | 2.3 MW | 1 | Grampian, Scotland | 2011 | Private Developer |
| Gairnieston Farm | 2.3 MW | 1 | Grampian, Scotland | 2010 | Private Developer |
| Mornflake Oats Wind Turbine | 2.3 MW | 1 | Grampian, Scotland | 2012 | Mornflake Oats/ Hamlyns Oats |
| Strath of Brydock - Extension | 2.3 MW | 1 | Grampian, Scotland | 2009 | Green Cat Renewables |
| Stroupster Wind Farm - additional turbine | 2.3 MW | 1 | Highland, Scotland | 2015 | Greencoat UK Wind/Bay Wa .r.e/ SunGift |
| Thorfinn Wind Farm - NM2000 | 2.3 MW | 2 | Orkney Islands, Scotland | 2000 | Vestas |
| The Rosti Factory | 2.2 MW | 1 | Strathclyde, Scotland | 2013 | Branna Industrial & Technical Services Ltd |
| Goathill Quarry Turbine | 2 MW | 1 | Fife, Scotland | 2015 | Collier Quarrying Group |
| Hill of Easterton Extension | 2 MW | 2 | Grampian, Scotland | 2007 | Mackies |
| West Hill, Flotta | 2 MW | 1 | Orkney Islands, Scotland | 2010 | Scotrenewables (Scotland) Ltd |
| Barns of Ayre Wind Turbines (2) | 1.8 MW | 2 | Orkney Islands, Scotland | 2013 | Ayre Energy/Aquatera Ltd |
| Flotta | 1.8 MW | 1 | Orkney Islands, Scotland | 2010 | Scotwind (Scottish Renewables) |
| Gallowhill | 1.8 MW | 2 | Orkney Islands, Scotland | 2013 | Private Developer |
| Myres Hill | 1.8 MW | 2 | Strathclyde, Scotland | 2001 | National Energy Laboratories (NEL) |
| Hill of Balquhindachy extension | 1.7 MW | 2 | Grampian, Scotland | 2010 | Private Developer |
| Upper Wheedlemont Farm | 1.7 MW | 2 | Grampian, Scotland | 2017 | J & A�Wilson Ltd |
| Easter Tolmauds | 1.6 MW | 2 | Grampian, Scotland | 2016 | Frank A Smart & Son Ltd |
| Myreton Crossroads | 1.6 MW | 2 | Grampian, Scotland | 2013 | Seren Energy |
| North Red Bog | 1.6 MW | 2 | Grampian, Scotland | 2008 | Green Cat Renewables |
| Bonerbo Wind Turbines | 1.5 MW | 3 | Fife, Scotland | 2014 | Messrs Stevenson, Watson and Brunton |
| Craigannet Farm Wind Turbine | 1.5 MW | 1 | Stirling, Scotland | 2017 | Clean Earth Energy |
| Easter Melrose Wind Energy Project | 1.5 MW | 3 | Grampian, Scotland | 2015 | Melrose Farms |
| F M C Land, Pitreavie Business Park | 1.5 MW | 1 | Fife, Scotland | 2011 | FMC Corp UK Ltd |
| Ferneylea Farm | 1.5 MW | 2 | East Lothian, Scotland | 2015 | CBK Galbraith |
| FMC Technologies | 1.5 MW | 2 | Fife, Scotland | 2011 | FMC Technologies |
| Hill of Lybster (Wind Turbine - Extension) | 1.5 MW | 1 | Highland, Scotland | 2021 | The Energy Workshop |
| Marshill Farm | 1.5 MW | 1 | Lanarkshire, Scotland | 2015 | Green Cat Renewables |
| Monan Hill Wind Turbines | 1.5 MW | 3 | Western Isles, Scotland | 2015 | North Harris Trust |
| Noble Foods | 1.5 MW | 1 | Fife, Scotland | 2014 | Wind Direct |
| Skeddoway Farm Wind Turbine | 1.5 MW | 1 | Fife, Scotland | 2014 | Clenergy |
| Southrigg | 1.5 MW | 1 | Lanarkshire, Scotland | 2016 | Southrigg WT |
| Thorfinn Wind Farm - NM1500 | 1.5 MW | 1 | Orkney Islands, Scotland | 2000 | Vestas |
| Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine | 1 MW | 1 | Angus, Scotland | 2023 | Arbikie Distillery |
| Moorhouse Farm | 1 MW | 2 | Borders, Scotland | 2018 | Urban Wind |
| New Holland | 1 MW | 2 | Orkney Islands, Scotland | 2014 | Windflow UK |
| Sunnyside wind cluster | 1 MW | 2 | Dumfries and Galloway, Scotland | 2015 | Sunnyside Wind Farm |
| Yonderton Farm | 1 MW | 2 | Grampian, Scotland | 2014 | Green Cat Renewables |
| Lower Rumster wind turbine | 0.2 MW | 3 | Highland, Scotland | 2021 | Ventus Renewables |
Onshore wind farms in England
282 operational onshore projects, 2.9 GW. See the wind farms in England guide for a map and the pipeline.
| Wind farm | Capacity | Turbines | Location | Operational | Operator / applicant |
|---|---|---|---|---|---|
| Keadby Wind Farm | 68 MW | 34 | Humberside, England | 2015 | Scottish and Southern Energy (SSE) |
| Fullabrook Down Wind Farm | 66 MW | 22 | Devon, England | 2012 | Devon Wind Power Ltd |
| Scout Moor Windfarm | 65 MW | 26 | Lancashire, England | 2008 | Munich Re (previously Peel) |
| Little Cheyne Court Wind Farm | 59.8 MW | 26 | Kent, England | 2009 | RWE npower |
| Ray Wind Farm | 54.4 MW | 16 | Northumberland, England | 2017 | Vattenfall |
| Middlemoor | 54 MW | 18 | Northumberland, England | 2013 | Npower Renewables |
| Frodsham Marsh | 50.4 MW | 19 | Cheshire, England | 2016 | Foresight/Belltown |
| Tween Bridge Windfarm | 44 MW | 22 | South Yorkshire, England | 2012 | E.ON Renewables |
| Green Rigg | 36 MW | 18 | Northumberland, England | 2012 | EDF/China General Nuclear Power Corporation |
| Goole Fields ll Wind Farm | 34.9 MW | 17 | Humberside, England | 2016 | RWE Npower Renewables |
| Sixpenny Wood Windfarm | 33 MW | 10 | Humberside, England | 2013 | Greencoat UK Wind |
| Goole Fields | 32.8 MW | 16 | Humberside, England | 2014 | RWE npower |
| Beck Burn | 31 MW | 9 | Cumbria, England | 2017 | EDF Energy Renewables |
| Lissett Airfield Wind Farm | 30 MW | 12 | Humberside, England | 2009 | Novera Energy |
| Fraisthorpe Wind Farm | 29.7 MW | 9 | Humberside, England | 2016 | Octopus Investments |
| Twin Rivers | 28.7 MW | 14 | Humberside, England | 2016 | NTR |
| Bicker Fen | 26.7 MW | 13 | Lincolnshire, England | 2008 | Wind Prospect |
| Lynemouth Windfarm (Resubmission) | 26 MW | 13 | Northumberland, England | 2012 | Scottish Power Renewables |
| Wadlow Wind Farm | 26 MW | 13 | Cambridgeshire, England | 2012 | DIF |
| Wryde Croft | 26 MW | 13 | Cambridgeshire, England | 2016 | Renewable Energy Systems (RES) |
| Hall Farm Routh | 24.6 MW | 12 | Humberside, England | 2013 | John Laing Environmental Assets Group/REG Power Management |
| Hyndburn Wind Farm | 24 MW | 12 | Lancashire, England | 2012 | Energiekontor UK |
| Red Tile | 24 MW | 12 | Cambridgeshire, England | 2006 | Wind Prospect Developments |
| Rusholme Wind Farm | 24 MW | 12 | North Yorkshire, England | 2010 | EDF/China General Nuclear Power Corporation |
| West Durham Wind Farm | 24 MW | 12 | County Durham, England | 2009 | ESBI |
| Crook Hill (Rochdale MBC) 2 of 2 | 23.8 MW | 7 | Greater Manchester, England | 2015 | Infrared Capital Partners |
| Swinford Wind Farm | 22 MW | 11 | Leicestershire, England | 2012 | Nuon UK |
| Middlewick wind farm | 20.7 MW | 9 | Essex, England | 2014 | Blue Energy (formerly Ridgewind Ltd) |
| Butterwick Moor | 20.5 MW | 10 | County Durham, England | 2011 | E.ON UK |
| Wandylaw | 20.5 MW | 10 | Northumberland, England | 2013 | Blue Energy |
| Bradwell Wind Farm (Repower) | 20 MW | 10 | Essex, England | 2013 | Npower Renewables |
| Burton Wold Windfarm | 20 MW | 10 | Northamptonshire, England | 2006 | Gravis Capital Management |
| Carland Cross Wind Farm Repowering | 20 MW | 10 | Cornwall, England | 2013 | Scottish Power Renewables |
| Cotton Farm | 20 MW | 8 | Cambridgeshire, England | 2013 | Greencoat UK Wind |
| Langford Wind Farm | 20 MW | 10 | Bedfordshire, England | 2014 | Co-operative Group |
| Penny Hill Lane | 19.8 MW | 6 | South Yorkshire, England | 2013 | Banks Renewables |
| North Steads Wind Farm | 18.5 MW | 9 | Northumberland, England | 2016 | Ventient (formerly Infinis) |
| Batsworthy Cross | 18 MW | 9 | Devon, England | 2016 | Blackrock Real Assets |
| Den Brook | 18 MW | 9 | Devon, England | 2016 | Aviva |
| Ovenden Moor (Repower) | 18 MW | 9 | West Yorkshire, England | 2017 | Yorkshire Windpower |
| Stags Holt | 18 MW | 9 | Cambridgeshire, England | 2007 | Powergen / Wind Prospects |
| Withernwick | 18 MW | 9 | Humberside, England | 2013 | Energiekontor UK |
| Turncole Wind Farm | 17.5 MW | 7 | Essex, England | 2016 | RES/ Aviva |
| Roos Wind Farm (Resubmission) | 17.1 MW | 9 | Humberside, England | 2013 | Renewable Energy Systems (RES) |
| Bishopthorpe | 16.4 MW | 8 | Lincolnshire, England | 2017 | Greencoat UK (formerly BayWa r.e.) |
| Deeping St Nicholas Wind Farm | 16.4 MW | 8 | Lincolnshire, England | 2006 | Wind Prospect Developments |
| Gayton Le Marsh Wind Farm | 16.4 MW | 8 | Lincolnshire, England | 2016 | Energiekontor UK |
| Bagmoor | 16 MW | 8 | Humberside, England | 2009 | Munich Re (previously Wind Prospect) |
| Caton Moor Windfarm Repowering | 16 MW | 8 | Lancashire, England | 2006 | Hainsford Energy |
| Coal Clough Wind Farm Repowering | 16 MW | 8 | Lancashire, England | 2015 | Coal Clough Wind Farm |
| Coldham | 16 MW | 8 | Cambridgeshire, England | 2005 | Wind Prospect / TXU |
| Fen Farm | 16 MW | 20 | Lincolnshire, England | 2008 | Ecotricity |
| Glass Moor | 16 MW | 8 | Cambridgeshire, England | 2005 | Fenland Windfarms Ltd |
| Knabs Ridge Windfarm | 16 MW | 8 | North Yorkshire, England | 2008 | RWE npower |
| Yelvertoft Wind Farm | 16 MW | 8 | Northamptonshire, England | 2013 | Greencoat UK Wind |
| Lindhurst Wind Farm | 15 MW | 5 | Nottinghamshire, England | 2010 | Npower Renewables |
| Sober Hill Wind Farm | 15 MW | 6 | Humberside, England | 2013 | West Coast Energy |
| Wingates Wind Farm | 15 MW | 6 | Northumberland, England | 2013 | Ventient (formerly Infinis) |
| Burton Wold Wind Farm - Northern Extension | 14.4 MW | 9 | Northamptonshire, England | 2014 | John Laing Environmental Assets Group |
| New Albion Wind Farm | 14.4 MW | 7 | Northamptonshire, England | 2016 | John Laing Environmental Assets Group |
| North Pickenham | 14.4 MW | 8 | Norfolk, England | 2006 | Foresight Group |
| Coldham Hall | 14 MW | 8 | Cambridgeshire, England | 2005 | Co-op |
| Milton Keynes Wind Farm | 14 MW | 7 | Buckinghamshire, England | 2010 | Gravis Capital Management |
| The Grange Wind Farm | 14 MW | 7 | Lincolnshire, England | 2013 | Renewable Energy Systems (RES) |
| Walkway | 14 MW | 7 | County Durham, England | 2008 | Wind Prospect |
| Whitemill Wind Farm | 14 MW | 7 | Cambridgeshire, England | 2012 | Co-operative Energy |
| Barmoor South Wind Farm | 13.8 MW | 6 | Northumberland, England | 2015 | EDF |
| Jack's Lane Wind Farm | 13.8 MW | 6 | Norfolk, England | 2015 | Aviva |
| Crook Hill (Calderdale MBC) 1 of 2 | 13.6 MW | 4 | Greater Manchester, England | 2015 | Infrared Capital Partners |
| Hallburn Farm | 13.2 MW | 6 | Cumbria, England | 2018 | REG Windpower/ BlackRock |
| Chelveston Renewable Energy Park Wind Farm (East Northamptonshire) | 12.5 MW | 5 | Northamptonshire, England | 2014 | Chelveston Renewable Energy |
| Kelmarsh Wind Farm (Resubmission) | 12.5 MW | 5 | Northamptonshire, England | 2016 | Blue Energy |
| Red Gap Moor Wind Farm | 12.5 MW | 5 | Cleveland, England | 2017 | Capital Dynamics |
| Spaldington Airfield | 12.5 MW | 5 | Humberside, England | 2016 | Falck Renewables |
| Watford Lodge | 12.5 MW | 5 | Northamptonshire, England | 2015 | Broadview Energy |
| Grange | 12.3 MW | 6 | Humberside, England | 2015 | Octopus Investements/Blue Energy |
| Todmorden Moor | 12.3 MW | 5 | West Yorkshire, England | 2014 | Todmorden Moor Wind Farm Ltd |
| Winwick | 12.3 MW | 6 | Northamptonshire, England | 2016 | Blue Energy |
| Armistead Wind Farm | 12 MW | 6 | Cumbria, England | 2013 | Banks Renewables |
| Gedney Marsh | 12 MW | 6 | Lincolnshire, England | 2008 | Wind Prospect |
| Glass moor Extension | 12 MW | 6 | Cambridgeshire, England | 2013 | EDF/China General Nuclear Power Corporation |
| Goonhilly Downs Wind Farm Repower | 12 MW | 6 | Cornwall, England | 2010 | REG Windpower (previously Cornwall Light & Power) |
| Kiln Pit Hill Windfarm | 12 MW | 6 | Northumberland, England | 2012 | Npower Renewables |
| Moor House Wind Farm | 12 MW | 6 | County Durham, England | 2017 | Banks Renewables |
| Tallentire Hill | 12 MW | 6 | Cumbria, England | 2013 | The Renewables Infrastructure Group (TRIG) |
| Tilbury Docks | 12 MW | 4 | Essex, England | 2013 | Scottish Equity Partners |
| Furness Wind Farm/High Winds (Harlock Repowering) | 11.5 MW | 5 | Cumbria, England | 2016 | Baywind Co-op & Energy4All & Belltown Power |
| Upper Holton Wind Farm | 11.5 MW | 5 | Suffolk, England | 2016 | Temporis Capital |
| Wharrels Hill Wind Farm | 10.4 MW | 8 | Cumbria, England | 2007 | Wharrels Hill Windfarm Ltd/ National Windpower |
| Boardinghouse Wind Farm | 10.3 MW | 5 | Cambridgeshire, England | 2015 | Ecogen |
| Earl's Hall | 10.3 MW | 5 | Essex, England | 2013 | Greencoat UK Wind |
| Hook Moor | 10.3 MW | 3 | West Yorkshire, England | 2016 | Banks Renewables |
| Stonish Hill (Bilsthorpe) | 10.3 MW | 5 | Nottinghamshire, England | 2013 | REG Power Management (John Laing/Peel Energy) |
| Burton Pidsea (Wadworth Hill) Wind Farm | 10.2 MW | 3 | Humberside, England | 2014 | Aeolian Holderness Ltd |
| Reaps Moss Wind Farm | 10.2 MW | 3 | Lancashire, England | 2015 | Infrared Capital Partners |
| Carn Vean | 10 MW | 5 | Cornwall, England | 2008 | Unknown |
| Chelveston Renewable Energy Park Wind Farm (Bedford) | 10 MW | 4 | Northamptonshire, England | 2014 | Chelveston Renewable Energy Ltd |
| Denzell Downs Wind Farm | 10 MW | 5 | Cornwall, England | 2015 | REG Windpower / BlackRock |
| Haswell Moor | 10 MW | 5 | County Durham, England | 2010 | E.ON UK Renewables Developments Ltd |
| Lilbourne Wind Farm | 10 MW | 5 | Northamptonshire, England | 2014 | Cetis |
| Port of Liverpool - wind | 10 MW | 4 | Merseyside, England | 2009 | Mersey Docks and Harbour Company |
| Sancton Hill | 10 MW | 5 | Humberside, England | 2012 | REG Windpower (previously Cornwall Light and Power) |
| St. Breock Re-Power | 10 MW | 5 | Cornwall, England | 2015 | REG & Blackrock |
| Woolley Hill Wind Farm | 10 MW | 4 | Cambridgeshire, England | 2014 | Aviva |
| Bears Down Wind Farm | 9.8 MW | 16 | Cornwall, England | 2001 | Natural Power |
| Bambers Farm | 9.6 MW | 8 | Lincolnshire, England | 2004 | Ecotricity |
| Coal Clough Wind Farm | 9.6 MW | 24 | Lancashire, England | 1993 | Renewable Energy Systems (RES) |
| Alaska Wind Farm | 9.2 MW | 4 | Dorset, England | 2025 | Alaska (formerly Purbeck Wind Farm LLP c/o Infinergy) |
| Delabole (Repowering) | 9.2 MW | 4 | Cornwall, England | 2011 | Good Energy Generation |
| Galsworthy Wind Park | 9.2 MW | 4 | Devon, England | 2014 | Ecotricity |
| Hellrigg Wind farm | 9.2 MW | 4 | Cumbria, England | 2011 | Npower Renewables |
| Avonmouth Port - extension | 9 MW | 3 | Avon, England | 2014 | Bristol Port Company |
| Hawton Wind Farm | 9 MW | 3 | Nottinghamshire, England | 2017 | Temporis Capital |
| Out Newton Wind Farm | 9 MW | 7 | Humberside, England | 2002 | Powergen Renewables Developments Ltd |
| Whittlesey | 9 MW | 3 | Cambridgeshire, England | 2008 | REG Windpower (previously Cornwall Light and Power) |
| New Rides Wind Farm | 8.8 MW | 4 | Kent, England | 2018 | Airvolution Energy |
| Winscales Phase I and II | 8.8 MW | 11 | Cumbria, England | 2004 | Cumbria Wind Farms |
| Airfield Farm (Podington) | 8.6 MW | 3 | Bedfordshire, England | 2017 | Airvolution Energy |
| Park Spring Wind Farm | 8.6 MW | 3 | South Yorkshire, England | 2015 | EDF Energy Renewables |
| Avonmouth Wind Power | 8.2 MW | 4 | Avon, England | 2014 | Wessex Water Engineering Services |
| Chiplow | 8.2 MW | 5 | Norfolk, England | 2016 | Blue Energy |
| Great Eppleton Farm Repowering | 8.2 MW | 4 | Tyne and Wear, England | 2010 | E.ON UK |
| Port of Sheerness Wind Farm (was Lappel Bank) | 8.2 MW | 4 | Kent, England | 2016 | Peel Energy |
| Sisters | 8.2 MW | 4 | Northumberland, England | 2016 | Infinis (formerly Novera Energy) |
| Withernwick extension | 8.2 MW | 4 | Humberside, England | 2019 | Energiekontor UK |
| Broom Hill Farm | 8 MW | 4 | County Durham, England | 2009 | EDF Energy |
| Carsington Pasture | 8 MW | 4 | Derbyshire, England | 2014 | Carsington Wind Energy Limited |
| Hampole Wind Farm | 8 MW | 4 | South Yorkshire, England | 2014 | Good Energy (previously nPower Renewables) |
| Lambs Hill | 8 MW | 4 | County Durham, England | 2017 | Banks Renewables |
| Langley Moor | 8 MW | 4 | County Durham, England | 2008 | EDF Energy |
| Low Spinney Wind Farm | 8 MW | 4 | Leicestershire, England | 2011 | Infinis, previously Broadview Energy Developments |
| Marr Windfarm | 8 MW | 4 | South Yorkshire, England | 2012 | Banks Renewables |
| Ramsey Wind Farm Extension | 8 MW | 4 | Cambridgeshire, England | 2015 | REG Windpower |
| Blackstone Edge | 7.5 MW | 3 | South Yorkshire, England | 2013 | Ventient (formerly Infinis) |
| Burton Wold Wind Farm South | 7.5 MW | 3 | Northamptonshire, England | 2017 | Infinergy/ Muirhall Energy |
| Dunsland Cross Wind Farm | 7.5 MW | 3 | Devon, England | 2017 | Temporis Capital |
| Far Marsh Farm | 7.5 MW | 3 | Humberside, England | 2017 | Private Developer |
| Hameldon Hill extension | 7.5 MW | 3 | Lancashire, England | 2013 | RWE NPower Renewables |
| Heysham South Wind Farm | 7.5 MW | 3 | Lancashire, England | 2015 | Banks Renewables |
| Shepham Lane | 7.5 MW | 3 | East Sussex, England | 2017 | Foresight |
| South Sharpley Wind Farm (Revised) | 7.5 MW | 3 | County Durham, England | 2013 | REG Windpower (previously Cornwall Light & Power) |
| Tedder Hill Wind cluster | 7.5 MW | 3 | Humberside, England | 2013 | Ventient (formerly Infinis) |
| Dalby | 7.2 MW | 9 | Leicestershire, England | 2016 | Ecotricity |
| M1 Wind Farm | 7.2 MW | 9 | Northamptonshire, England | 2014 | Wind Prospect Developments |
| Alveston Wind Park | 6.9 MW | 3 | Avon, England | 2017 | Ecotricity |
| Spicer Hill Wind Farm | 6.9 MW | 3 | South Yorkshire, England | 2013 | J G Pears Limited |
| Cold Northcott | 6.6 MW | 22 | Cornwall, England | 2002 | Otter Power |
| Fairfield Farm | 6.5 MW | 5 | Cumbria, England | 2011 | Windprospect |
| Lambrigg Wind Farm | 6.5 MW | 5 | Cumbria, England | 2001 | Lambrigg Windfarm Ltd |
| Westmill Wind Farm | 6.5 MW | 5 | Oxfordshire, England | 2008 | Private Developer |
| Common Barn Wind Farm | 6.2 MW | 3 | Cambridgeshire, England | 2019 | TCI Renewables |
| Land at Flimby Hall Farm | 6.2 MW | 3 | Cumbria, England | 2013 | Flimby Wind Energy Ltd |
| Westnewton | 6.2 MW | 3 | Cumbria, England | 2014 | Broadview Energy Limited |
| Avonmouth Port | 6 MW | 3 | Avon, England | 2007 | Bristol Port Authority |
| Boundary Lane | 6 MW | 3 | County Durham, England | 2013 | EDF |
| Burnt House Farm | 6 MW | 3 | Cambridgeshire, England | 2013 | Fivestone Ltd |
| Hazlehead | 6 MW | 3 | South Yorkshire, England | 2011 | Banks Renewables |
| Potato Pot Wind Farm | 6 MW | 3 | Cumbria, England | 2016 | Capital Dynamics |
| Ranson Moor (phase 1) | 6 MW | 3 | Cambridgeshire, England | 2007 | Fenpower Limited |
| Seamer Windfarm - Stockton on Tees | 6 MW | 3 | County Durham, England | 2012 | Broadview Energy |
| Winscales Moor | 6 MW | 7 | Cumbria, England | 2009 | Gravis Capital Management |
| Ford Wind Park - Dagenham | 5.9 MW | 2 | London, England | 2004 | Ecotricity |
| Royd Moor | 5.9 MW | 13 | South Yorkshire, England | 1993 | Unknown |
| High Volts Wind Farm | 5.5 MW | 3 | Cleveland, England | 2003 | E.ON UK |
| Oldside Wind Farm | 5.4 MW | 9 | Cumbria, England | 1996 | Windprospect / Windcluster |
| High Hedley Hope 2 (Extension) | 5.2 MW | 4 | County Durham, England | 2008 | EDF Energy |
| Southern Law | 5.2 MW | 4 | County Durham, England | 2008 | EDF Energy |
| Trimdon Grange | 5.2 MW | 4 | County Durham, England | 2008 | Cumbria Wind Farms |
| Avonmouth Port II | 5 MW | 2 | Avon, England | 2013 | Bristol City Council - Energy Management Unit |
| Derby Sewage Treatment Works | 5 MW | 2 | Derbyshire, England | 2014 | Severn Trent Water |
| Humphrey Group | 5 MW | 2 | Suffolk, England | 2013 | Roy Humphrey Group |
| Melton Common Wind Cluster | 5 MW | 2 | Humberside, England | 2017 | Seneca Global Energy |
| Melton Waste Park | 5 MW | 2 | Humberside, England | 2017 | Seneca Global Energy |
| Ryder Point Quarry Wind Turbines | 5 MW | 2 | Derbyshire, England | 2015 | Longcliffe Quarries |
| Kirkby Moor | 4.8 MW | 12 | Cumbria, England | 1993 | Npower Renewables |
| Lowca Wind Farm | 4.7 MW | 7 | Cumbria, England | 2000 | Windprospect |
| Askam | 4.6 MW | 7 | Cumbria, England | 1999 | Cannock Renewables |
| Bambers II | 4.6 MW | 6 | Lincolnshire, England | 2006 | Ecotricity Limited |
| HMP Standford Hill | 4.6 MW | 2 | Kent, England | 2013 | Resonance |
| Newton Marsh Wind Project | 4.6 MW | 2 | Lincolnshire, England | 2014 | TCI Renewables |
| Woodlands Barton Wind Project | 4.6 MW | 2 | Cornwall, England | 2014 | Private Developer |
| Four Burrows Wind Farm | 4.5 MW | 15 | Cornwall, England | 1998 | Renewable Energy Systems (RES) |
| Loscar Farm | 4.5 MW | 3 | South Yorkshire, England | 2011 | REG Windpower (previously Cornwall Light and Power) |
| New Barn Farm | 4.5 MW | 3 | Lancashire, England | 2007 | Private Developer |
| Severn Road | 4.2 MW | 1 | Avon, England | 2023 | Ambition Community Energy |
| Siddick Wind Farm | 4.2 MW | 7 | Cumbria, England | 1996 | Windprospect / Windcluster |
| Checkley Wood Farm | 4.1 MW | 1 | Bedfordshire, England | 2024 | AW Group |
| Wind Farm Africa Alive | 4.1 MW | 2 | Suffolk, England | 2011 | SLP Energy |
| East Youlstone Wind Farm | 4 MW | 2 | Devon, England | 2015 | Airvolution Energy |
| Eastman Chemicals, Workington | 4 MW | 2 | Cumbria, England | 2006 | Unknown |
| French Farm | 4 MW | 2 | Cambridgeshire, England | 2016 | REG Windpower (previously Cornwall Light and Power) |
| Garlenick Estate 2 - Wind Turbines | 4 MW | 2 | Cornwall, England | 2015 | Airvolution Energy |
| Great Orton | 4 MW | 6 | Cumbria, England | 1999 | Cumbria Wind Farms |
| Greencroft Estate Turbines | 4 MW | 2 | County Durham, England | 2013 | Lanchester Properties |
| High Haswell Wind Farm | 4 MW | 2 | County Durham, England | 2011 | Hallam Land Management |
| M1 J18 Wind Turbines | 4 MW | 2 | Northamptonshire, England | 2014 | Airvolution Energy |
| MSD Cramlington | 4 MW | 2 | Northumberland, England | 2011 | Unknown |
| Nissan Wind Farm | 4 MW | 6 | Tyne and Wear, England | 2005 | Nissan Manufacturing UK |
| North Pickenham Airfield | 4 MW | 2 | Norfolk, England | 2014 | Bernard Matthews Green Energy |
| Orchard End | 4 MW | 2 | Lancashire, England | 2013 | Renewable Energy Generation |
| Ranson Moor Wind Farm (Phase 2) | 4 MW | 2 | Cambridgeshire, England | 2007 | EcoGen Projects / Fenpower |
| Rodbaston | 4 MW | 2 | Staffordshire, England | 2017 | REG Windpower |
| Seamer Wind Farm - Hambleton | 4 MW | 2 | Cleveland, England | 2012 | Infinis, previously Broadview Energy |
| High Pow Farm | 3.9 MW | 3 | Cumbria, England | 2007 | REG Windpower (previously Cornwall Light and Power) |
| Weston Airfield Wind Turbines | 3.6 MW | 2 | Norfolk, England | 2015 | Bernard Matthews |
| Blyth Harbour Wind Farm (re-power) | 3.4 MW | 1 | Northumberland, England | 2012 | Hainsford Energy |
| Otterham Down Wind Farm | 3.2 MW | 4 | Cornwall, England | 2011 | Otter Power |
| Croda Chemicals Europe | 3 MW | 1 | Humberside, England | 2008 | Croda Chemicals |
| Energy Works Hull - Wind Turbine | 3 MW | 1 | Humberside, England | 2018 | Spencer Group |
| Great Eppleton Wind Farm | 3 MW | 4 | Tyne and Wear, England | 1997 | Border Windfarm Limited / AMEC |
| Royal Seaforth Dock Wind Farm | 3 MW | 6 | Merseyside, England | 1999 | Mersey Docks and Harbour Company and Windcluster Limited |
| Holmside Hall | 2.8 MW | 2 | County Durham, England | 2004 | E.ON UK |
| Blyth Harbour Wind Farm | 2.7 MW | 9 | Northumberland, England | 1992 | Border Wind Farms Ltd |
| Hare Hill (B) | 2.7 MW | 2 | County Durham, England | 2004 | Powergen |
| Advanced Manufacturing Research Centre | 2.6 MW | 2 | South Yorkshire, England | 2009 | Unknown |
| Darracott Moor | 2.6 MW | 3 | Devon, England | 2011 | Gresham House |
| High Sharpley Wind Farm | 2.6 MW | 2 | County Durham, England | 2006 | REG Windpower (previously Cornwall Light & Power) |
| The Hollies | 2.6 MW | 2 | Lincolnshire, England | 2008 | National Wind Power |
| Tow Law Wind Farm | 2.6 MW | 3 | County Durham, England | 2001 | RWE npower |
| Accolade Wines | 2.5 MW | 1 | Avon, England | 2019 | Clean Earth Energy |
| Crossness Sewage Works Turbine | 2.5 MW | 1 | London, England | 2014 | Thames Water Utilities |
| Harlock Hill Wind Farm | 2.5 MW | 5 | Cumbria, England | 1997 | The Wind Company |
| Newthorpe Wind Turbine | 2.5 MW | 1 | Nottinghamshire, England | 2014 | Severn Trent Water |
| Severn Trent STW | 2.5 MW | 1 | Leicestershire, England | 2014 | Severn Trent Water |
| Crimp Wind Farm | 2.4 MW | 3 | Cornwall, England | 2011 | Crimp Power Ltd (West Coast Energy) |
| Haverigg Extension Wind Farm | 2.4 MW | 4 | Cumbria, England | 1998 | The Wind Company |
| Hedley Hope | 2.4 MW | 3 | County Durham, England | 2001 | Border Wind |
| Bewick Drift | 2.3 MW | 1 | Northumberland, England | 2013 | Harworth Power |
| Great Orton Wind Farm (Extension) | 2.3 MW | 6 | Cumbria, England | 2000 | Great Orton Wind Farms (II) Ltd |
| Land near Ventonteague | 2.3 MW | 1 | Cornwall, England | 2020 | Cornwall Council |
| Mawdesley Moss | 2.3 MW | 3 | Lancashire, England | 2012 | Private Developer |
| Ness point Wind Turbine 1 | 2.3 MW | 1 | Suffolk, England | 2004 | SLP Energy |
| Sibelco Brassington | 2.3 MW | 1 | Derbyshire, England | 2016 | Sibelco/ Golconda |
| Wythegill Wind Turbine | 2.3 MW | 1 | Cumbria, England | 2015 | Airvolution Energy |
| Beckton Sewage Treatment Works | 2.2 MW | 2 | London, England | 2014 | Thames Water Utilities |
| Celcon Blocks Ltd | 2 MW | 1 | Humberside, England | 2016 | Ecotricity / Next Generation |
| Dewlay Cheese Wind Turbine | 2 MW | 1 | Lancashire, England | 2010 | Dewlay Cheese Company |
| Ford Motor Company Ltd (Extension) | 2 MW | 1 | London, England | 2011 | Unknown |
| Green Park | 2 MW | 1 | Berkshire, England | 2005 | Ecotricity / Prudential |
| Lancaster University (wind) | 2 MW | 1 | Lancashire, England | 2013 | Lancaster University |
| Long Hill Road | 2 MW | 1 | Cambridgeshire, England | 2005 | Snow Mountain Investment Ltd |
| MARCH SEWAGE TREATMENT WORKS - WIND TURBINE | 2 MW | 1 | Cambridgeshire, England | 2012 | TCI Renewables |
| Nissan Motors Plant Extn | 2 MW | 3 | Tyne and Wear, England | 2008 | TNEI Services Ltd |
| Sharpness Docks | 2 MW | 1 | Gloucestershire, England | 2017 | Partnerships for Renewables/AGR |
| Shooters Bottom Wind Park | 2 MW | 1 | Somerset, England | 2008 | Ecotricity |
| Stags Holt Extension | 2 MW | 1 | Cambridgeshire, England | 2010 | E.ON UK |
| Worksop - B&Q | 2 MW | 1 | Nottinghamshire, England | 2009 | Ecotricity |
| The Low Carbon Energy Generation Project at Keele University | 1.9 MW | 2 | Staffordshire, England | 2021 | Keele University |
| Kirkheaton Wind Farm | 1.8 MW | 3 | Northumberland, England | 2000 | Border Wind Farms Ltd /AMEC |
| Ramsey 1 | 1.8 MW | 1 | Cambridgeshire, England | 2008 | REG Windpower |
| Swaffham Plashes II | 1.8 MW | 1 | Norfolk, England | 2003 | Ecotricity |
| Roskrow Wind Turbines | 1.7 MW | 2 | Cornwall, England | 2007 | REG Windpower (previously Cornwall Light and Power) |
| The Limes Wind Turbines | 1.7 MW | 2 | Humberside, England | 2015 | Broadview Energy |
| Halifax Farm | 1.6 MW | 1 | Leicestershire, England | 2015 | Wentworth and Harper |
| Orton Park Farm | 1.6 MW | 2 | Cumbria, England | 2017 | Orton Park Wind Energy |
| Blue Gates Farm | 1.5 MW | 1 | Essex, England | 2010 | M H Leyland Ltd |
| Boddington Reservoir | 1.5 MW | 1 | Northamptonshire, England | 2014 | Unknown |
| Double Arches Quarry Wind Turbine | 1.5 MW | 1 | Bedfordshire, England | 2014 | Arnold White Estates (AWE Renewables) |
| Fanny House Farm/Heysham Moss | 1.5 MW | 1 | Lancashire, England | 2015 | Blue Energy |
| Greenvale AP Wind Turbine | 1.5 MW | 1 | Cambridgeshire, England | 2014 | Greenvale AP |
| K L Technologies Wind Turbine | 1.5 MW | 1 | Norfolk, England | 2013 | KL Technology Limited |
| Marston Vale Country Park Wind Turbine | 1.5 MW | 1 | Bedfordshire, England | 2014 | Blue Energy |
| Nethercott Farm | 1.5 MW | 3 | Devon, England | 2016 | Private Developer |
| Newstead and Annesley Wind Turbine | 1.5 MW | 1 | Nottinghamshire, England | 2016 | Redpath Energy |
| Quarrendon Fields | 1.5 MW | 1 | Buckinghamshire, England | 2014 | AWE Renewables |
| Severn Trent Water - Stoke Bardolph Wind Turbine | 1.5 MW | 1 | Nottinghamshire, England | 2015 | Severn Trent Water |
| South Beach Wind Turbine (Somerton) | 1.5 MW | 1 | Norfolk, England | 2000 | Ecotricity |
| Swaffham 1 - Ecotech Wind Park | 1.5 MW | 1 | Norfolk, England | 1999 | LRZ Ltd (Taken over by NOVERA) |
| Chelker Reservoir | 1.3 MW | 4 | North Yorkshire, England | 1992 | Yorkshire Water |
| Hare Hill | 1.3 MW | 1 | County Durham, England | 2004 | E.ON UK |
| Loftsome Bridge | 1.3 MW | 2 | Humberside, England | 2008 | Yorkshire Water |
| Norton Fields Farm | 1.3 MW | 1 | Hereford and Worcester, England | 2015 | REsense c/o CO2Sense |
| Saltend Wind Turbine | 1.3 MW | 1 | Humberside, England | 2007 | Yorkshire Water |
| Chelker Reservoir (Retention of Turbines) | 1.2 MW | 4 | North Yorkshire, England | 2004 | Yorkshire Water |
| Haverigg Repowering (Haverigg II) | 1.2 MW | 5 | Cumbria, England | 2004 | Windprospect |
| The Haven | 1.2 MW | 1 | Hereford and Worcester, England | 2003 | Private Developer |
| Bloodhills - repowering | 1 MW | 2 | Norfolk, England | 2015 | The Farm Energy Partnership LLP |
| East Midlands Airport | 1 MW | 4 | Leicestershire, England | 2011 | Wind Direct |
| Goonabarn Farm Wind Turbines | 1 MW | 2 | Cornwall, England | 2016 | George Richards Farms Partnership |
| Little Belhus Restoration Site | 1 MW | 2 | Essex, England | 2016 | Constantine Wind Energy |
| Mounteneys and Cherry Rock Wind Turbines | 1 MW | 2 | Gloucestershire, England | 2017 | Resilient Energy Mounteneys Renewables |
| PROMISED LAND FARM | 1 MW | 2 | Merseyside, England | 2014 | Private Developer |
Onshore wind farms in Wales
72 operational onshore projects, 1.2 GW. See the wind farms in Wales guide for a map and the pipeline.
| Wind farm | Capacity | Turbines | Location | Operational | Operator / applicant |
|---|---|---|---|---|---|
| Pen Y Cymoedd | 228 MW | 76 | Neath Port Talbot, Wales | 2017 | Vattenfall (previously Nuon Renewables) |
| Clocaenog Forest Wind Farm | 96 MW | 32 | Clwyd, Wales | 2019 | RWE Innogy UK |
| Cefn Croes Wind Farm | 58.5 MW | 39 | Dyfed, Wales | 2005 | Renewable Development Company Ltd, KENTECH Ltd |
| Brechfa Forest West | 57.4 MW | 28 | Dyfed, Wales | 2018 | RWE Npower Renewables |
| Brenig Wind Farm | 37.6 MW | 16 | Denbighshire, Wales | 2018 | CGNEE |
| Mynydd y Betws | 34.5 MW | 15 | Dyfed, Wales | 2013 | ESB (Cambrian Renewable Energy Ltd / Betws Common Holdings Ltd) |
| Garreg Lwyd | 34 MW | 17 | Powys, Wales | 2017 | Renewables Infrastructure Group (TRIG) |
| Mynydd Y Gwair Wind Farm | 32.8 MW | 16 | West Glamorgan, Wales | 2019 | RWE Npower Renewables/ Innogy |
| Ffynnon Oer Wind Farm | 32 MW | 16 | West Glamorgan, Wales | 2005 | RWE npower |
| Llandinam Windfarm | 31 MW | 103 | Powys, Wales | 1993 | CELTPOWER LTD |
| Maesgwyn | 26 MW | 13 | West Glamorgan, Wales | 2011 | Pennant Wind Energy Ventures |
| Pant y wal | 25 MW | 10 | Mid Glamorgan, Wales | 2013 | Pennant Wind Energy Ventures (PWEV) |
| Tirgwynt | 24.6 MW | 12 | Powys, Wales | 2017 | Foresight |
| Llynfi Renewable Energy Park, Land at Mynydd Caerau | 24 MW | 12 | Neath Port Talbot, Wales | 2017 | John Laing Environmental Assets Group |
| Maerdy | 24 MW | 8 | Mid Glamorgan, Wales | 2013 | Greencoat UK Wind |
| Blaengwen | 23 MW | 10 | Dyfed, Wales | 2009 | Statkraft and Catamount Energy Corporation |
| Mynydd Bwllfa Wind Farm - Resubmission | 22.5 MW | 9 | Mid Glamorgan, Wales | 2015 | Pennant Walters |
| Tir Mostyn And Foel Goch Wind Farm | 21.3 MW | 25 | Clwyd, Wales | 2005 | Munich Re (previously Windjen Power Ltd) |
| Llanbabo Wind Farm | 20.4 MW | 9 | Gwynedd, Wales | 1997 | MANWEB Generation Holdings |
| Pant y wal extension | 20 MW | 8 | Mid Glamorgan, Wales | 2017 | Pennant Walters (PYWX) |
| Fforch Nest Wind Farm pt2 | 17.5 MW | 7 | Mid Glamorgan, Wales | 2013 | Pennant Walters |
| Carno 'A' Wind Farm | 16.8 MW | 28 | Powys, Wales | 1996 | RWE npower |
| Carno 'B' Wind Farm | 16.8 MW | 28 | Powys, Wales | 1996 | RWE npower |
| Bryn Du | 16.4 MW | 39 | Powys, Wales | 2005 | Renewable Development Company Ltd |
| Carno 'A'and 'B' Wind Farm, (Extension) | 15.6 MW | 12 | Powys, Wales | 2009 | RWE npower |
| Cemmaes 'C' Wind Farm | 15.3 MW | 18 | Powys, Wales | 2002 | Vestas |
| Mynydd Clogau Wind Farm | 14.5 MW | 17 | Powys, Wales | 2005 | Renewable Energy Systems (RES) |
| Bryn Blaen Wind Farm | 13.8 MW | 6 | Powys, Wales | 2019 | Njord Energy |
| Mynydd Portref Wind Farm extension | 12 MW | 6 | Mid Glamorgan, Wales | 2017 | REG Windpower |
| Moel Maelogen A Phase 2 | 11.7 MW | 8 | Gwynedd, Wales | 2008 | John Laing Environmental Assets Group |
| Mynydd Gorddu Wind Farm | 10.2 MW | 19 | Dyfed, Wales | 1998 | Cynllun Trydan Gwynt |
| Fforch Nest Wind Farm pt1 | 10 MW | 4 | Mid Glamorgan, Wales | 2013 | Pennant Walters |
| Bryn titli Windfarm | 9.9 MW | 22 | Powys, Wales | 1994 | Innogy |
| Llangwyryfon | 9.4 MW | 11 | Dyfed, Wales | 2004 | Westbury Windfarms |
| Mynydd Portref | 9.4 MW | 11 | Mid Glamorgan, Wales | 2012 | Gresham House |
| Wern Ddu Wind Farm | 9.2 MW | 4 | Clwyd, Wales | 2010 | Tegni |
| Taff Ely Wind Farm | 9 MW | 20 | Mid Glamorgan, Wales | 1993 | Npower Renewables |
| Parc Cynog Extension | 8.4 MW | 6 | Dyfed, Wales | 2009 | Nuon |
| Wear Point | 8.2 MW | 4 | Dyfed, Wales | 2014 | John Laing Environmental Assets Group |
| Mynydd Brombil Wind Farm | 8 MW | 4 | Neath Port Talbot, Wales | 2017 | REG Windpower |
| Penrhys Wind Farm/Ferndale Power Factory | 6.4 MW | 8 | Mid Glamorgan, Wales | 2011 | John Laing Environmental Assets Group |
| Llynfi Afan Renewable Energy Park | 6 MW | 3 | Neath Port Talbot, Wales | 2017 | John Laing Environmental Assets Group |
| Trysglwyn Wind Farm | 5.6 MW | 14 | Gwynedd, Wales | 1996 | RWE npower |
| Dyffryn Brodyn Wind Farm | 5.5 MW | 11 | Dyfed, Wales | 1994 | Renewable Energy Systems (RES) |
| Newton Down | 5 MW | 2 | Mid Glamorgan, Wales | 2016 | Renewable Energy Partnerships Ltd |
| Solutia UK Ltd | 5 MW | 2 | Gwent, Wales | 2009 | Solutia / Vestas |
| Mynydd Y Gwrhyd Windfarm | 4.7 MW | 2 | West Glamorgan, Wales | 2017 | Awel Aman Tawe Community Energy |
| Ystgellog Farm Wind Farm | 4.6 MW | 2 | Gwynedd, Wales | 2013 | Airvolution Energy |
| Oakdale Business Park | 4 MW | 2 | Gwent, Wales | 2013 | Resonance |
| Pen Bryn Oer Wind Farm | 4 MW | 3 | Mid Glamorgan, Wales | 2018 | REG Windpower/ BlackRock |
| Blaen Bowi Wind Farm | 3.9 MW | 3 | Dyfed, Wales | 2002 | WINDJEN POWER LTD |
| Braich Ddu | 3.9 MW | 3 | Gwynedd, Wales | 2007 | REG Windpower (previously Cornwall Light and Power) |
| Parc-Cynog Wind Farm | 3.6 MW | 5 | Dyfed, Wales | 2001 | Micon Wind Turbines (UK) Limited |
| Longlands Farm, Rush Wall Lane | 3.5 MW | 1 | Gwent, Wales | 2021 | Clean Earth (CE) |
| Cemmaes 'B' Wind Farm | 3.4 MW | 6 | Powys, Wales | 2002 | Vestas |
| Castle Pill - Repowering | 3.2 MW | 4 | Dyfed, Wales | 2009 | John Laing Environmental Assets Group |
| Hafoty Ucha '2' and '3' Wind Turbine | 2.6 MW | 3 | Clwyd, Wales | 2002 | Private Developer |
| Moel Maelogen A | 2.6 MW | 2 | Gwynedd, Wales | 2003 | John Laing Environmental Assets Group |
| Graig Fatha Farm | 2.5 MW | 1 | Rhondda Cynon Taff, Wales | 2021 | Cleanearth |
| Maesgwyn Wind Farm - extension | 2.5 MW | 1 | West Glamorgan, Wales | 2016 | Pennant Walters (MAESX) Limited |
| Nash Waste Water Treatment Works Turbine | 2.5 MW | 1 | Gwent, Wales | 2017 | Welsh Water |
| Parc Stormy, Stormy Down | 2.5 MW | 1 | Mid Glamorgan, Wales | — | Cenin Renewables |
| Rheidol Wind Farm | 2.4 MW | 8 | Dyfed, Wales | 1997 | Powergen |
| ANP Newport Wind Turbine | 2.3 MW | 2 | Gwent, Wales | 2016 | Associated British Ports |
| G24 Innovations Turbine | 2.3 MW | 1 | South Glamorgan, Wales | 2011 | G24 Innovations Limited |
| Kingspan | 1.8 MW | 2 | Flintshire, Wales | 2019 | Kingspan |
| Lawrence Landfill | 1.6 MW | 2 | Dyfed, Wales | 2017 | Wind Energy Direct |
| Princes Gate Spring Water | 1.6 MW | 2 | Dyfed, Wales | 2014 | Princes Gate Spring Water |
| Bodtegir | 1.5 MW | 1 | Clwyd, Wales | 2017 | Clean Earth Energy |
| Longlands Lane | 1.5 MW | 1 | Gwent, Wales | 2014 | Renewable Energy Systems (RES) |
| West of Rhiwfelin Fach Farm | 1.5 MW | 1 | Mid Glamorgan, Wales | 2018 | Infinite Renewables |
| Lodge Farm 1 | 1 MW | 1 | Dyfed, Wales | 2006 | Private Developer |
Onshore wind farms in Northern Ireland
83 operational onshore projects, 1.2 GW. See the wind farms in Northern Ireland guide for a map and the pipeline.
| Wind farm | Capacity | Turbines | Location | Operational | Operator / applicant |
|---|---|---|---|---|---|
| Slieve Rushen Extension | 54 MW | 18 | Co. Fermanagh, Northern Ireland | 2008 | Unknown |
| Windyhill Road (Dunbeg) Wind Farm | 42 MW | 14 | Co. Derry / Londonderry, Northern Ireland | 2014 | Gaelectric Developments/ CGN Europe Energy |
| Pollnalaght (Cornavarrow) | 38.4 MW | 12 | Co. Tyrone, Northern Ireland | 2018 | Energia |
| Brockaghboy Wind Farm | 37.5 MW | 15 | Co. Derry / Londonderry, Northern Ireland | 2017 | Greencoat |
| Tievenameenta | 34.5 MW | 15 | Co. Tyrone, Northern Ireland | 2017 | Scottish and Southern Energy (SSE) |
| Crighshane | 32.2 MW | 14 | Co. Tyrone, Northern Ireland | 2012 | Greencoat (formerly Energia Renewables) |
| Curraghamulkin (Dooish Wind Farm) | 30 MW | 10 | Co. Tyrone, Northern Ireland | 2018 | DW Consultancy |
| Slieve Divena Phase 1 Wind Farm | 30 MW | 12 | Co. Tyrone, Northern Ireland | 2009 | Greencoat (formerly Infinis/SSE) |
| Long Mountain | 27.6 MW | 12 | Co. Antrim, Northern Ireland | 2016 | Energia Renewables |
| Slieve Kirk | 27.6 MW | 12 | Co. Tyrone, Northern Ireland | 2011 | Scottish and Southern Energy (SSE) |
| Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) | 27.6 MW | 12 | Co. Derry / Londonderry, Northern Ireland | 2013 | Scottish and Southern Energy (SSE) |
| Altahullion | 26 MW | 20 | Co. Derry / Londonderry, Northern Ireland | 2003 | Renewable Energy Systems (RES) / BP Energy |
| Castlecraig | 25 MW | 10 | Co. Tyrone, Northern Ireland | 2018 | Renewable Energy Systems (RES) |
| Gruig Wind Farm | 25 MW | 10 | Co. Antrim, Northern Ireland | 2009 | Foresight Group |
| Craiggore windfarm | 23.5 MW | 10 | Co. Derry / Londonderry, Northern Ireland | — | Renewable Energy Systems (RES) |
| Callagheen | 22.8 MW | 13 | Co. Fermanagh, Northern Ireland | 2005 | B9 / Renewable Energy Systems (RES) |
| Elginny Hill | 22 MW | 11 | Co. Antrim, Northern Ireland | 2018 | Brookfields (Antrim Wind Energy) |
| Dunmore | 21 MW | 7 | Co. Derry / Londonderry, Northern Ireland | 2013 | TCI Renewables |
| Rathsherry | 21 MW | 9 | Co. Antrim, Northern Ireland | 2018 | Energia (formerly Brookfield Renewable Energy Group) |
| Glengesh Lower Forest (Murley) | 20.7 MW | 9 | Co. Tyrone, Northern Ireland | 2024 | Renewable Energy Systems (RES) |
| Townlands of Carrickatane | 20.7 MW | 9 | Co. Derry / Londonderry, Northern Ireland | 2013 | Northern Wind Power |
| Hunter's Hill | 20 MW | 8 | Co. Tyrone, Northern Ireland | 2010 | Wind Farm Developments / RES UK & Ireland |
| Land approx 75m South of 141 | 20 MW | 8 | Co. Tyrone, Northern Ireland | 2007 | Private Developer |
| Screggagh | 19.5 MW | 8 | Co. Tyrone, Northern Ireland | 2011 | Screggagh Windfarm |
| Tappaghan | 19.5 MW | 13 | Co. Fermanagh, Northern Ireland | 2005 | Greencoat UK Wind |
| Slieve Divena Phase 2 Wind Farm | 18.8 MW | 8 | Co. Tyrone, Northern Ireland | 2017 | Scottish and Southern Energy (SSE) |
| Church Hill | 18.4 MW | 8 | Co. Tyrone, Northern Ireland | 2012 | Greencoat (formerly Energia Renewables) |
| Slieve Kirk (formerly Glenconway) | 18.4 MW | 8 | Co. Derry / Londonderry, Northern Ireland | 2013 | Scottish and Southern Energy (SSE) |
| Altaveedan Wind Farm | 17.9 MW | 6 | Co. Antrim, Northern Ireland | 2017 | NTR PLC |
| Shantavny Scotch | 16.1 MW | 7 | Co. Tyrone, Northern Ireland | 2017 | Tyrone Wind Energy Ltd |
| Crockagarran | 15 MW | 6 | Co. Tyrone, Northern Ireland | 2010 | ESB |
| Crockandun | 15 MW | 6 | Co. Derry / Londonderry, Northern Ireland | 2017 | Brookfield Renewable Energy Group |
| Curryfree Wind Farm | 15 MW | 6 | Co. Derry / Londonderry, Northern Ireland | 2011 | ESB |
| Garves Mountain Farm | 15 MW | 5 | Co. Antrim, Northern Ireland | 2009 | Gravis Capital Management |
| Gortfinbar | 15 MW | 6 | Co. Tyrone, Northern Ireland | 2016 | Energia Renewables |
| Molly Mountain | 15 MW | 5 | Co. Fermanagh, Northern Ireland | 2014 | Erne Concrete Pumping |
| Ora More | 15 MW | 6 | Co. Fermanagh, Northern Ireland | 2017 | Natural Power |
| Carn Hill | 13.8 MW | 6 | Co. Antrim, Northern Ireland | 2013 | Gaelectric Developments/ CGN Europe Energy |
| Cregganconroe | 13.8 MW | 6 | Co. Tyrone, Northern Ireland | 2017 | Gaelectric Developments/ CGN Europe Energy |
| Eglish Mountain | 13.8 MW | 6 | Co. Tyrone, Northern Ireland | 2017 | ESB (Northern Wind Power) |
| Inishative | 13.8 MW | 6 | Co. Tyrone, Northern Ireland | 2017 | Gaelectric Developments/ CGN Europe Energy |
| Seegronan | 13.8 MW | 6 | Co. Tyrone, Northern Ireland | 2016 | Seegronan Windfarm |
| Crockdun | 12.5 MW | 5 | Co. Tyrone, Northern Ireland | 2017 | ESB (Northern Wind Power) |
| Cloonty Wind Farm | 12 MW | 4 | Co. Antrim, Northern Ireland | 2016 | Gaelectric Developments/ CGN Europe Energy |
| Monnaboy Wind Farm | 12 MW | 4 | Co. Derry / Londonderry, Northern Ireland | 2015 | Gaelectric Developments/ CGN Europe Energy |
| Altahullion Phase II | 11.7 MW | 9 | Co. Derry / Londonderry, Northern Ireland | 2007 | B9 Energy / RES |
| Teiges | 11 MW | 5 | Co. Fermanagh, Northern Ireland | 2018 | Energia |
| Lough Hill | 10.5 MW | 6 | Co. Tyrone, Northern Ireland | 2006 | B9 / Renewable Energy Systems (RES) |
| Brockaghboy Wind Farm - extension | 10 MW | 4 | Co. Derry / Londonderry, Northern Ireland | 2017 | Greencoat |
| Thornog Windfarm | 9.2 MW | 4 | Co. Tyrone, Northern Ireland | 2014 | Energia Renewables |
| Thornog Windfarm Extension | 9.2 MW | 4 | Co. Tyrone, Northern Ireland | 2014 | Energia Renewables |
| Bessy Bell Extension | 9 MW | 6 | Co. Tyrone, Northern Ireland | 2008 | Bessy Bell Windfarm |
| Bin Mountain | 9 MW | 6 | Co. Tyrone, Northern Ireland | 2007 | Greencoat UK Wind |
| Tappaghan Extension | 9 MW | 6 | Co. Fermanagh, Northern Ireland | 2009 | Greencoat UK Wind |
| Wolf Bog Wind Farm | 8.8 MW | 5 | Co. Antrim, Northern Ireland | 2007 | B9 Energy / RES |
| Crockbaravally Wind Farm | 7.5 MW | 3 | Co. Tyrone, Northern Ireland | 2017 | Golden Square Energy |
| Lendrum's Bridge Wind Farm ( Extension 2) | 7.3 MW | 11 | Co. Tyrone, Northern Ireland | 2002 | Renewable Energy Systems (RES) |
| Altamuskin | 7.1 MW | 3 | Co. Tyrone, Northern Ireland | 2017 | Altamuskin Windfarm (Energia) |
| Altamuskin Extension | 7.1 MW | 3 | Co. Tyrone, Northern Ireland | 2017 | Altamuskin Windfarm (Energia) |
| Eshmore | 6.9 MW | 3 | Co. Tyrone, Northern Ireland | 2016 | Energia Renewables |
| Glenbuck | 6.9 MW | 3 | Co. Antrim, Northern Ireland | 2017 | Energia Renewables |
| Slieveglass | 6.9 MW | 3 | Co. Tyrone, Northern Ireland | 2018 | Slieveglass wind farm (Energia) |
| Draperstown (Brackagh) Wind Farm | 6 MW | 3 | Co. Derry / Londonderry, Northern Ireland | 2017 | Renewable Energy Generation (REG) |
| Lendrum's Bridge Wind Farm | 5.9 MW | 9 | Co. Tyrone, Northern Ireland | 2000 | Renewable Energy Systems (RES) |
| Owenreagh Extension | 5.1 MW | 6 | Co. Tyrone, Northern Ireland | 2008 | EF Energy |
| Bessy Bell Wind Farm | 5 MW | 10 | Co. Tyrone, Northern Ireland | 1995 | Colham Energy Ltd, plus Airtricty extrension |
| Corby Knowe | 5 MW | 3 | Co. Antrim, Northern Ireland | 2017 | Gaelectric Developments/ CGN Europe Energy |
| Corkey Wind Farm | 5 MW | 10 | Co. Antrim, Northern Ireland | 1994 | B9 Energy Services Ltd/ ScottishPower Renewables |
| Elliot's Hill Wind Farm | 5 MW | 10 | Co. Antrim, Northern Ireland | 1995 | B9 Energy Services Ltd/ ScottishPower Renewables |
| Owenreagh Wind Farm | 5 MW | 10 | Co. Tyrone, Northern Ireland | 1997 | EF Energy |
| Rigged Hill Wind Farm | 5 MW | 10 | Co. Derry / Londonderry, Northern Ireland | 1994 | B9 Energy Services Ltd/ ScottishPower Renewables |
| Slieve Rushen Phase 1 Wind Farm | 5 MW | 10 | Co. Fermanagh, Northern Ireland | 1995 | Sean Quinn Group |
| Ballymena Wind Park Limited | 4.7 MW | 2 | Co. Antrim, Northern Ireland | 2013 | White Young Green Planning |
| Clondermot Turbines | 4.6 MW | 2 | Co. Derry / Londonderry, Northern Ireland | 2015 | Energia Renewables |
| The Michelin Tyre Factory - Ballymena | 4.6 MW | 2 | Co. Antrim, Northern Ireland | 2013 | Ecotricity |
| Corkey Wind Farm Extension | 2.5 MW | 1 | Co. Antrim, Northern Ireland | 2017 | Northern Ireland Renewables |
| Crockagarron Ext | 2.5 MW | 1 | Co. Tyrone, Northern Ireland | 2012 | Northern Wind Power� |
| Glenbuck | 2.3 MW | 1 | Co. Antrim, Northern Ireland | 2017 | Energia Renewables |
| Wind Turbine 1 | 2.3 MW | 1 | Co. Antrim, Northern Ireland | 2011 | Brett Martin Ltd |
| Crockbrack | 2 MW | 1 | Co. Tyrone, Northern Ireland | 2017 | Gaelectric Developments/ CGN Europe Energy |
| Connaught Road | 1.7 MW | 2 | Co. Antrim, Northern Ireland | 2012 | Lowlands Health & Energy Ltd� |
| Magherafelt | 1 MW | 1 | Co. Derry / Londonderry, Northern Ireland | 2015 | Tobermore Concrete Products |
| Dundrinne Road | 0.2 MW | 1 | Co. Down, Northern Ireland | — | Private Developer |
Onshore wind farms in the pipeline
703 onshore projects (20.1 GW) are under construction, consented or awaiting a planning decision. Browse them in wind farms under construction and proposed wind farms, or search every record in the wind farm database.
Frequently asked questions
How many onshore wind farms are there in the UK?
The July 2026 REPD lists 785 operational onshore wind projects with 15.5 GW of capacity and 7,353 turbines. 696 have two or more turbines.
What is the largest onshore wind farm in the UK?
Viking Wind Farm is the largest operational onshore wind project in the REPD at 443 MW with 103 turbines.
Which nation has the most onshore wind farms?
Scotland has the most operational onshore wind projects, with 348.
How many onshore wind farms are planned?
703 onshore projects totalling 20.1 GW are under construction, consented or in planning.
Sources and method
Figures come from the July 2026 extract of the Department for Energy Security and Net Zero's Renewable Energy Planning Database (REPD), which tracks UK renewable projects through planning, construction and operation. Each figure is calculated directly from the source records and refreshes when a new snapshot is imported.
The REPD counts project records, not physical sites. Extensions, repowering schemes and later phases can appear as separate records, and very small turbines below the database threshold are not included. Status reflects the snapshot date; developers' later announcements can differ. Read the full methodology and limitations.