Operationalonshore · July 2026 REPD 4141

Westnewton

Warwick Hall Farm, Westnewton, Cumbria. CA7 3PF, Cumbria, North West, England

Capacity6.2 MW
Turbines3
Per turbine2.1 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
England
Region
North West
Site address
Warwick Hall Farm, Westnewton, Cumbria. CA7 3PF
Latitude
54.779502
Longitude
-3.346309
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorBroadview Energy Limited
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Cumberland
Application reference
2/2008/0997
Application submitted
24 Dec 2008
Permission granted
4 Feb 2011

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

No verified Elexon match yet

We have not published a project-to-BM-unit relationship. Candidate matches never appear as measured generation.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated21 Jul 2014
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects