Operationalonshore · REPD 4643

Kype Muir Wind Farm

approximately 5 km south of the town of Strathaven, Strathclyde, Scotland, Scotland

Capacity88.4 MW
Turbines26
Per turbine3.4 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
approximately 5 km south of the town of Strathaven
Latitude
55.632652
Longitude
-4.036105
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorBanks Renewables
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Scottish Government (S36)
Application reference
EK/11/0256
Application submitted
9 Aug 2011
Permission granted
22 May 2014

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated1 Oct 2019
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland