Operationalonshore · REPD 3738

Port of Sheerness Wind Farm (was Lappel Bank)

Sheerness Docks, Sheerness, Kent, Kent, South East, England

Capacity8.2 MW
Turbines4
Per turbine2.1 MW
Max height125 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
England
Region
South East
Site address
Sheerness Docks, Sheerness, Kent
Latitude
51.443046
Longitude
0.747873
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorPeel Energy
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Swale
Application reference
SW/08/0896
Application submitted
26 Aug 2008
Permission granted
11 Mar 2009

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated24 Oct 2016
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in South East