Operationalonshore · REPD 4111

Eshmore

Crockanavark, Eshmore and Altaglushan Townlands , Galbally, Dungannon. Co Tyrone, Co. Tyrone, Northern Ireland, Northern Ireland

Capacity6.9 MW
Turbines3
Per turbine2.3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Northern Ireland
Region
Northern Ireland
Site address
Crockanavark, Eshmore and Altaglushan Townlands , Galbally, Dungannon. Co Tyrone
Latitude
55.98697
Longitude
-9.915402
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorEnergia Renewables
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Mid Ulster
Application reference
M/2006/1802/F
Application submitted
9 Oct 2006
Permission granted
19 Oct 2011

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated4 Jan 2017
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Northern Ireland