Operationalonshore · REPD 4605

Blary Hill Wind Farm

Land North Of Loch Arnicle (including C20 To The A83T) Barr Glen By Glenbarr Argyll And Bute, Strathclyde, Scotland, Scotland

Capacity35 MW
Turbines14
Per turbine2.5 MW
Max height110 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Land North Of Loch Arnicle (including C20 To The A83T) Barr Glen By Glenbarr Argyll And Bute
Latitude
55.568256
Longitude
-5.643539
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorRenewables Infrastructure Group / Renewable Energy Systems (RES)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Argyll and Bute
Application reference
14/01978/PP
Application submitted
22 Aug 2014
Permission granted
23 Jun 2017

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated16 Jan 2026
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland