Operationalonshore · July 2026 REPD 4011

Clyde Wind Farm

Clyde Wind farm, Lowther Hills, between Crawford and Nether Howecleuch, NW of Lockerbie, Strathclyde, Scotland, Scotland

Capacity350 MW
Turbines152
Per turbine2.3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Clyde Wind farm, Lowther Hills, between Crawford and Nether Howecleuch, NW of Lockerbie
Latitude
55.441634
Longitude
-3.542734
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorScottish and Southern Energy (SSE)/ Greencoat UK Wind
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Scottish Government (S36)
Application reference
Not recorded
Application submitted
1 Oct 2004
Permission granted
21 Jul 2008

Project timeline

Became operational

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

No verified Elexon match yet

We have not published a project-to-BM-unit relationship. Candidate matches never appear as measured generation.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated1 Jun 2018
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects