Operationalonshore · REPD 4449

Solwaybank Wind Farm

Allfornought Hill, Langholm, Dumfries & Galloway (8 km south-west of Langholm and 12 km north of Gretna), Dumfries and Galloway, Scotland, Scotland

Capacity30 MW
Turbines15
Per turbine2 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Allfornought Hill, Langholm, Dumfries & Galloway (8 km south-west of Langholm and 12 km north of Gretna)
Latitude
55.100174
Longitude
-3.107751
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorThe Renewables Infrastructure Group (TRIG)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Dumfries and Galloway
Application reference
11/P/4/0354
Application submitted
8 Nov 2011
Permission granted
24 Sept 2014

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated25 May 2022
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland