Operationalonshore · REPD 3835

Roos Wind Farm (Resubmission)

Land To The West Of Ivy House Rectory Road Roos East Riding Of Yorkshire, Humberside, Yorkshire and Humber, England

Capacity17.1 MW
Turbines9
Per turbine1.9 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
England
Region
Yorkshire and Humber
Site address
Land To The West Of Ivy House Rectory Road Roos East Riding Of Yorkshire
Latitude
53.751753
Longitude
-0.0697
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorRenewable Energy Systems (RES)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
East Riding of Yorkshire
Application reference
08/05692/STPLFE
Application submitted
20 Jan 2009
Permission granted
13 May 2010

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated4 Jun 2013
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects