Operationalonshore · July 2026 REPD 7312

The Low Carbon Energy Generation Project at Keele University

Land Adj To Springpool Wood, Keele, Newcastle-Under-Lyme, Staffordshire, West Midlands, England

Capacity1.9 MW
Turbines2
Per turbineNot recorded
Max height77 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
England
Region
West Midlands
Site address
Land Adj To Springpool Wood, Keele, Newcastle-Under-Lyme
Latitude
53.00191
Longitude
-2.271024
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorKeele University
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Newcastle-under-Lyme
Application reference
18/00933/FUL
Application submitted
20 Dec 2018
Permission granted
2 May 2019

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

No verified Elexon match yet

We have not published a project-to-BM-unit relationship. Candidate matches never appear as measured generation.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated1 Sept 2021
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects