Operationalonshore · REPD 4371

Glen Kyllachy Wind Farm

10 miles south of Inverness, 3 miles south-east of the B851 and 3 miles west of the A9 trunk road and village of Tomatin, Highland, Scotland, Scotland

Capacity48.5 MW
Turbines20
Per turbine2.5 MW
Max height110 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
10 miles south of Inverness, 3 miles south-east of the B851 and 3 miles west of the A9 trunk road and village of Tomatin
Latitude
57.320732
Longitude
-4.08565
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorGreencoat UK Wind
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Highland
Application reference
13/02441/FUL
Application submitted
28 Jun 2013
Permission granted
22 Apr 2015

Project timeline

Became operational

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated23 Aug 2022
Contains public sector information licensed under the Open Government Licence v3.0.