Operationalonshore · July 2026 REPD 3096

Little Cheyne Court Wind Farm

Little Cheyne Court, Romney Marsh Near Lydd Kent, Kent, South East, England

Capacity59.8 MW
Turbines26
Per turbine2.3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
England
Region
South East
Site address
Little Cheyne Court, Romney Marsh Near Lydd Kent
Latitude
50.963823
Longitude
0.822737
Turbine manufacturer
Nordex
Turbine model
Nordex N90

Turbine make and model from Wikipedia lists of onshore wind farms in the UK (Wikipedia contributors, CC BY-SA 4.0), matched to this REPD record. See UK wind turbine manufacturers.

02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorRWE npower
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Folkestone and Hythe
Application reference
YO2/1278/SH
Application submitted
28 Nov 2002
Permission granted
18 Oct 2005

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

No verified Elexon match yet

We have not published a project-to-BM-unit relationship. Candidate matches never appear as measured generation.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated9 Jul 2009
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in South East