Operationalonshore · July 2026 REPD 4409

Pant y wal extension

Mynydd Maesteg, Mynydd Pwlle yr Helog, Ogmore Vale, Rhondda Valley, Mid Glamorgan, Wales, Wales

Capacity20 MW
Turbines8
Per turbine2.5 MW
Max height125 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Wales
Region
Wales
Site address
Mynydd Maesteg, Mynydd Pwlle yr Helog, Ogmore Vale, Rhondda Valley
Latitude
51.587228
Longitude
-3.522043
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorPennant Walters (PYWX)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Bridgend
Application reference
P/14/293/FUL
Application submitted
30 Apr 2014
Permission granted
2 Apr 2015

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

No verified Elexon match yet

We have not published a project-to-BM-unit relationship. Candidate matches never appear as measured generation.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated21 Aug 2017
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Wales