Operationalonshore · July 2026 REPD 4015

Ewe Hill

Near Langham and Lockerbie Dumfries, Dumfries and Galloway, Scotland, Scotland

Capacity13.8 MW
Turbines6
Per turbine2.3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Near Langham and Lockerbie Dumfries
Latitude
55.107092
Longitude
-3.333869
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorScottish Power Renewables
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Scottish Government (S36)
Application reference
IEC3/107
Application submitted
7 Apr 2004
Permission granted
7 Jun 2010

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

No verified Elexon match yet

We have not published a project-to-BM-unit relationship. Candidate matches never appear as measured generation.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated26 Oct 2016
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects