Operationalonshore · REPD 3827

Newton Marsh Wind Project

Newton Marsh Sewage Treatment Works, Tetney, North-East Lincolnshire, Lincolnshire, East Midlands, England

Capacity4.6 MW
Turbines2
Per turbine2.3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
England
Region
East Midlands
Site address
Newton Marsh Sewage Treatment Works, Tetney, North-East Lincolnshire
Latitude
53.509288
Longitude
0.00901
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorTCI Renewables
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
East Lindsey
Application reference
N/178/03348/07
Application submitted
29 Jan 2008
Permission granted
28 May 2009

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated30 Apr 2014
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in East Midlands