Operationalonshore · REPD 3191

Garves Mountain Farm

Garves Mountain Farm, Tullaghans Road (access adjacent to no. 91), Dunloy. Ballymoney, Co. Antrim, Northern Ireland, Northern Ireland

Capacity15 MW
Turbines5
Per turbine3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Northern Ireland
Region
Northern Ireland
Site address
Garves Mountain Farm, Tullaghans Road (access adjacent to no. 91), Dunloy. Ballymoney
Latitude
56.428476
Longitude
-9.488554
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorGravis Capital Management
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Causeway Coast and Glens
Application reference
D/2003/0329/F
Application submitted
11 Jun 2003
Permission granted
20 Nov 2006

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated4 Dec 2017
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Northern Ireland