Operationalonshore · REPD 6324

Burnfoot East Wind Farm (further extension)

Site West Of Burnfoot Hill, High Street, Tillicoultry, Central, Clackmannanshire, Scotland, Scotland

Capacity10.8 MW
Turbines3
Per turbine3.6 MW
Max height135 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Site West Of Burnfoot Hill, High Street, Tillicoultry, Central
Latitude
56.209114
Longitude
-3.759967
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorWind Prospect Developments
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Clackmannanshire
Application reference
17/00026/FULL
Application submitted
30 Jan 2017
Permission granted
27 Mar 2019

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated15 Feb 2024
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects