Operationalonshore · July 2026 REPD 5555

ANP Newport Wind Turbine

Land To South Of South Dock, Alexandra Docks, And Adjacent to River Usk, East Way Road, Gwent, Wales, Wales

Capacity2.3 MW
Turbines2
Per turbine2.3 MW
Max height126 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
Wales
Region
Wales
Site address
Land To South Of South Dock, Alexandra Docks, And Adjacent to River Usk, East Way Road
Latitude
51.555914
Longitude
-2.973815
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorAssociated British Ports
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Newport
Application reference
15/0839
Application submitted
24 Jul 2015
Permission granted
30 Sept 2015

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

No verified Elexon match yet

We have not published a project-to-BM-unit relationship. Candidate matches never appear as measured generation.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated24 Oct 2016
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Wales