Operationalonshore · REPD 3992

Burton Pidsea (Wadworth Hill) Wind Farm

Land North East Of Wadworth Hill House Greens Lane Burton Pidsea East Riding Of Yorkshire, Humberside, Yorkshire and Humber, England

Capacity10.2 MW
Turbines3
Per turbine3.4 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Onshore wind
Country
England
Region
Yorkshire and Humber
Site address
Land North East Of Wadworth Hill House Greens Lane Burton Pidsea East Riding Of Yorkshire
Latitude
53.749196
Longitude
-0.113482
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorAeolian Holderness Ltd
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
East Riding of Yorkshire
Application reference
08/02928/STPLFE
Application submitted
29 May 2008
Permission granted
3 Sept 2009

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated20 Jan 2014
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Yorkshire and Humber