Operationaloffshore · REPD 2545

Westermost Rough A

25 km north of Spurn Head at the River Humber estuary., Offshore, Offshore, England

Capacity210 MW
Turbines35
Per turbine6 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Offshore wind
Country
England
Region
Offshore
Site address
25 km north of Spurn Head at the River Humber estuary.
Latitude
53.09773
Longitude
0.561481
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorOrsted (formerly Dong Energy)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
DECC (S36)
Application reference
Not recorded
Application submitted
17 Nov 2009
Permission granted
29 Nov 2011

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated5 Apr 2018
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More offshore projects in Offshore