Operationaloffshore · REPD 2534

Moray East

Smith Bank, Moray Firth - 13miles off Lybster, Offshore, Offshore, Scotland

Capacity950 MW
Turbines100
Per turbine9.5 MW
Max height204 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Offshore wind
Country
Scotland
Region
Offshore
Site address
Smith Bank, Moray Firth - 13miles off Lybster
Latitude
57.967325
Longitude
-2.790537
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorDiamond Green Limited, CTG & Ocean Winds
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Scottish Government (S36)
Application reference
Not recorded
Application submitted
28 Aug 2012
Permission granted
19 Mar 2014

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated12 Apr 2023
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More offshore projects in Offshore