Gunfleet Sands Offshore Wind Scheme

Gunfleet Sands 4 miles offshore from Holland-on-Sea Nr Clacton-on-Sea Essex, Offshore, Offshore, England

Capacity108 MW
Turbines30
Per turbine3.6 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Operational
Technology
Offshore wind
Country
England
Region
Offshore
Site address
Gunfleet Sands 4 miles offshore from Holland-on-Sea Nr Clacton-on-Sea Essex
Latitude
51.730818
Longitude
1.218012
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorOrsted (formerly Dong Energy)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
DECC (S36)
Application reference
Not recorded
Application submitted
1 Mar 2002
Permission granted
1 Mar 2004

Project timeline

Became operational

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated1 May 2018
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More offshore projects in Offshore