Awaiting Constructionoffshore · July 2026 REPD 10919

Morgan Offshore Wind Farm

30km offshore in the Irish Sea, Offshore, Offshore, England

Capacity1,500 MW
Turbines96
Per turbine15.7 MW
Max height364 m
Developer and planning context

Understanding this project

Morgan is an Irish Sea offshore development historically developed by EnBW and bp, subsequently described by EnBW as a partnership with JERA Nex bp.

Editorial review: . The dated statements below supplement the July 2026 REPD snapshot; they do not overwrite its fields or certify today’s construction status.

Where is it?

Irish Sea. The recorded map coordinate is a reference point, not the offshore development boundary.

Development position

EnBW announced on 15 January 2026 that it would not continue Morgan and Mona after neither secured support in the latest CfD round. This is a dated announcement of EnBW’s withdrawal; it does not establish the subsequent intentions of every partner.

Capacity and turbines

The July 2026 REPD record below lists 1,500 MW and 96 turbines. Treat these as recorded development parameters, not installed capacity or confirmed final design.

Related projects and phases

Morgan and Mona are separate projects. EnBW’s announcement describes 3 GW across both; that total must not be attributed to Morgan alone.

Primary sources

Explore UK offshore wind farms · Ask about this project’s data

01

Project overview

Core identity and development data from the current public snapshot.

Development status
Awaiting Construction
Technology
Offshore wind
Country
England
Region
Offshore
Site address
30km offshore in the Irish Sea
Latitude
Not recorded
Longitude
Not recorded
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorBP Oil UK Limited / ENBW UK Limited
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
The Planning Inspectorate - National Infrastructure
Application reference
EN010136
Application submitted
26 Apr 2024
Permission granted
29 Aug 2025

Project timeline

Planning permission granted

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

Not yet operational

Measured generation will only be considered after the project is operational and a BM-unit relationship is reviewed.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated3 Mar 2026
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More offshore projects in Offshore