Planning Permission Expiredonshore · REPD 3639

Linburn Farm

Linburn Farm B743 From U751 Tardoes Crossflat To U731 Greenock Water Muirkirk, Strathclyde, Scotland, Scotland

Capacity1.7 MW
Turbines2
Per turbine0.9 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Planning Permission Expired
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Linburn Farm B743 From U751 Tardoes Crossflat To U731 Greenock Water Muirkirk
Latitude
55.530172
Longitude
-4.119604
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorPrivate Developer
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
East Ayrshire
Application reference
14/0229/PP
Application submitted
18 Mar 2014
Permission granted
5 Nov 2015

Project timeline

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated31 Oct 2019
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland