Awaiting Constructiononshore · REPD 4987

Land to the north west of Hill of Petty

Hill of Petty, Fyvie, Turriff, Grampian, Aberdeenshire, Scotland, Scotland

Capacity3.6 MW
Turbines4
Per turbine0.9 MW
Max height67 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Awaiting Construction
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Hill of Petty, Fyvie, Turriff, Grampian
Latitude
57.412985
Longitude
-2.416931
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorGreen Cat Renewables
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Aberdeenshire
Application reference
APP/2015/0112
Application submitted
26 Jan 2015
Permission granted
18 Feb 2016

Project timeline

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated25 Oct 2018
Contains public sector information licensed under the Open Government Licence v3.0.