Application Submittedonshore · REPD 14997

Killean Wind Farm

1.8km east of Tayinloan, Kintyre, Tarbert, Strathclyde, Scotland, Scotland

Capacity59.4 MW
Turbines9
Per turbine6.6 MW
Max height180 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Submitted
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
1.8km east of Tayinloan, Kintyre, Tarbert
Latitude
55.648221
Longitude
-5.619248
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorRES Limited
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Scottish Government (S36)
Application reference
ECU00004927
Application submitted
15 Aug 2024
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated14 Oct 2024
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland