Awaiting Constructionoffshore · REPD 11851

Green Volt - Offshore Wind Farm

INTOG 6, North East Coast off Scotland, Offshore, Offshore, Scotland

Capacity560 MW
Turbines35
Per turbine16 MW
Max height270 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Awaiting Construction
Technology
Offshore wind
Country
Scotland
Region
Offshore
Site address
INTOG 6, North East Coast off Scotland
Latitude
57.154431
Longitude
-2.008727
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorFlotation Energy / V�rgr�nn
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Marine Scotland
Application reference
Not recorded
Application submitted
20 Jan 2023
Permission granted
19 Apr 2024

Project timeline

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated28 May 2024
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More offshore projects in Offshore