Application Refusedonshore · REPD 4585

Glencassley Wind Farm

approximately 12km north-west of Lairg, in Sutherland, Highland, Scotland, Scotland

Capacity69 MW
Turbines23
Per turbine3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Refused
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
approximately 12km north-west of Lairg, in Sutherland
Latitude
58.066978
Longitude
-4.654773
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorScottish and Southern Energy (SSE)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Scottish Government (S36)
Application reference
Not recorded
Application submitted
10 Jul 2012
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated1 Dec 2015
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland