Application Refusedonshore · REPD 6459

Faw Side Community Wind Farm

Land 6.7km North of Langholm and 17.8 km south west of Hawick, Dumfries and Galloway, Scotland, Scotland

Capacity315 MW
Turbines45
Per turbine7 MW
Max height200 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Refused
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Land 6.7km North of Langholm and 17.8 km south west of Hawick
Latitude
55.253873
Longitude
-3.024124
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorCommunity Windpower
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Scottish Government (S36)
Application reference
ECU00001833
Application submitted
22 May 2019
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated9 Jan 2024
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland