Project overview

Core identity and development data from the current public snapshot.

Development status
Revised
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Druim Leathann Windfarm North, Lochside, North Tolsta, Isle Of Lewis,
Latitude
58.347738
Longitude
-6.2503
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorBayWa r.e. (formerly Forsa)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Na h-Eileanan Siar
Application reference
17/00282/PPDM
Application submitted
2 Jun 2017
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated28 May 2020
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland