Under Constructionoffshore · REPD 2517

Dogger Bank C (was Teesside A)

125km off coast of Yorkshire, Offshore, Offshore, England

Capacity1,200 MW
Turbines87
Per turbine14 MW
Max height260 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Under Construction
Technology
Offshore wind
Country
England
Region
Offshore
Site address
125km off coast of Yorkshire
Latitude
55.209993
Longitude
2.329999
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorSSE/Equinor (formerly Statoil, formerly Forewind)
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
The Planning Inspectorate - National Infrastructure
Application reference
EN010051
Application submitted
28 Mar 2014
Permission granted
5 Aug 2015

Project timeline

Construction commenced

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated12 Apr 2022
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More offshore projects in Offshore