Awaiting Constructiononshore · REPD 13646

Divot Hill Wind Farm

Margree Area, 7km To The Ne/O St Johns Town Of Dalry, Castle Douglas, Dumfries and Galloway, Scotland, Scotland

CapacityNot recorded
Turbines9
Per turbineNot recorded
Max height200 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Awaiting Construction
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Margree Area, 7km To The Ne/O St Johns Town Of Dalry, Castle Douglas
Latitude
55.14184
Longitude
-4.11001
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorEnergiekontor (UK) Limited
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Dumfries and Galloway
Application reference
23/0368/FUL
Application submitted
24 Mar 2023
Permission granted
10 Jul 2024

Project timeline

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated18 Jul 2024
Contains public sector information licensed under the Open Government Licence v3.0.