Revisedonshore · REPD 6249

Cairnandrew Wind Farm

Land 500 meters East/South-East of Cairnandrew, Longmanhill, King Edward, Aberdeenshire, Scotland, Scotland

Capacity1.5 MW
Turbines3
Per turbine0.5 MW
Max height77 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Revised
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Land 500 meters East/South-East of Cairnandrew, Longmanhill, King Edward
Latitude
57.631313
Longitude
-2.417706
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operator1 Stop Renewables/King Edward Community Services
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Aberdeenshire
Application reference
APP/2016/1848
Application submitted
27 Jun 2016
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated30 Nov 2016
Contains public sector information licensed under the Open Government Licence v3.0.