Planning Permission Expiredonshore · REPD 5956

Brackenhills Farm

Land at Brackenhills Farm, Cornhill, Banff,, Aberdeenshire, Scotland, Scotland

Capacity2.3 MW
Turbines1
Per turbine2.3 MW
Max height100 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Planning Permission Expired
Technology
Onshore wind
Country
Scotland
Region
Scotland
Site address
Land at Brackenhills Farm, Cornhill, Banff,
Latitude
57.623625
Longitude
-2.69976
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorJ and LC Beattie Ltd
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Aberdeenshire
Application reference
APP/2015/3800
Application submitted
16 Dec 2015
Permission granted
6 Dec 2016

Project timeline

Planning permission granted

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated27 Apr 2020
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Scotland