Appeal Refusedonshore · REPD 6343

Penyrheol Las Farm

Pen Yr Heol Las Farm, Heol Las, Caerphilly, Mid Glamorgan, Caerphilly, Wales, Wales

Capacity1 MW
Turbines2
Per turbine0.5 MW
Max height74 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Appeal Refused
Technology
Onshore wind
Country
Wales
Region
Wales
Site address
Pen Yr Heol Las Farm, Heol Las, Caerphilly, Mid Glamorgan
Latitude
51.612273
Longitude
-3.246666
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorPrivate Developer
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Caerphilly
Application reference
17/0218/FULL
Application submitted
23 Mar 2017
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated28 Mar 2018