Appeal Withdrawnonshore · REPD 3848

Llys Dymper Wind Farm

Land at Llys Dymper, Gwytherin, Llanrwst, Conwy, Clwyd, Wales, Wales

Capacity23 MW
Turbines10
Per turbine2.3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Appeal Withdrawn
Technology
Onshore wind
Country
Wales
Region
Wales
Site address
Land at Llys Dymper, Gwytherin, Llanrwst, Conwy
Latitude
53.114285
Longitude
-3.668509
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorWindpower Wales
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Conwy
Application reference
0/38695
Application submitted
16 Feb 2012
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated9 Dec 2015
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Wales