Application Withdrawnonshore · REPD 6261

Dobies Business Park

Dobies Business Park, Lillyhall, Workington, Cumbria, North West, England

Capacity1.6 MW
Turbines4
Per turbine0.4 MW
Max height48 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Withdrawn
Technology
Onshore wind
Country
England
Region
North West
Site address
Dobies Business Park, Lillyhall, Workington
Latitude
54.608832
Longitude
-3.525744
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorDobies Cumbria
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Cumberland
Application reference
2/2016/0715
Application submitted
5 Nov 2016
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated1 Feb 2017
Contains public sector information licensed under the Open Government Licence v3.0.