Application Withdrawnonshore · July 2026 REPD 4224

Delph Wind Farm

Vine House Farm Worths Farm and Porters Farm, Deeping St Nicholas, Spalding, Lincolnshire, East Midlands, England

Capacity27 MW
Turbines9
Per turbine3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Withdrawn
Technology
Onshore wind
Country
England
Region
East Midlands
Site address
Vine House Farm Worths Farm and Porters Farm, Deeping St Nicholas, Spalding
Latitude
52.69501
Longitude
0.067801
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorWind Ventures
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Fenland
Application reference
H14-0110-13
Application submitted
13 Feb 2013
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

Not yet operational

Measured generation will only be considered after the project is operational and a BM-unit relationship is reviewed.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated28 Jul 2014