Application Submittedoffshore · REPD 13417

Cluaran Deas Ear / Ayre Wind Farm (Thistle South East) (NE2)

33km offshore from Orkney, Offshore, Scotland, Scotland

Capacity1,008 MW
Turbines67
Per turbine15 MW
Max height326 m
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Submitted
Technology
Offshore wind
Country
Scotland
Region
Scotland
Site address
33km offshore from Orkney
Latitude
Not recorded
Longitude
Not recorded
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorThistle Wind Partners
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Marine Scotland
Application reference
Not recorded
Application submitted
27 Nov 2025
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated13 Jul 2026
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More offshore projects in Scotland

Awaiting Constructionoffshore

Ossian

Scotland, Scotland

Capacity3,600 MW
Turbines 265
View project
Application Submittedoffshore

Marram

Scotland, Scotland

Capacity3,000 MW
Turbines
View project