Application Withdrawnonshore · REPD 2772

Chelker Reservoir Repower

Skipton Road, Addingham, Ilkley, LS29 0JU, North Yorkshire, Yorkshire and Humber, England

Capacity3.9 MW
Turbines3
Per turbine1.3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Withdrawn
Technology
Onshore wind
Country
England
Region
Yorkshire and Humber
Site address
Skipton Road, Addingham, Ilkley, LS29 0JU
Latitude
53.962097
Longitude
-1.91068
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorKelda Water Services
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
North Yorkshire
Application reference
24/2011/11383
Application submitted
11 Feb 2011
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Measured values will only appear after the project-to-BM-unit match is reviewed.

Measured generation unavailable

This project has not yet been linked to a verified Elexon BM unit. We do not estimate generation or capacity factor in the beta.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated16 Dec 2011
Contains public sector information licensed under the Open Government Licence v3.0.