Application Submittedonshore · July 2026 REPD 4570

Bryngydfa Wind Farm

Felindre (Northern Area SO135809, South Knighton) Powys LD7 1Y, Powys, Wales, Wales

Capacity36 MW
Turbines12
Per turbine3 MW
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Application Submitted
Technology
Onshore wind
Country
Wales
Region
Wales
Site address
Felindre (Northern Area SO135809, South Knighton) Powys LD7 1Y
Latitude
52.419226
Longitude
-3.273336
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorPrivate Developer
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
Powys
Application reference
P/2009/0384
Application submitted
3 Apr 2009
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

Not yet operational

Measured generation will only be considered after the project is operational and a BM-unit relationship is reviewed.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated16 Sept 2014
Contains public sector information licensed under the Open Government Licence v3.0.
Related projects

More onshore projects in Wales