Appeal Refusedonshore · July 2026 REPD 2984

Beech Tree Farm

Beech Tree Farm , Goveton , Kingsbridge , TQ7 2DT (Land between Goveton and A381), Devon, South West, England

Capacity4 MW
Turbines3
Per turbineNot recorded
Max heightNot recorded
01

Project overview

Core identity and development data from the current public snapshot.

Development status
Appeal Refused
Technology
Onshore wind
Country
England
Region
South West
Site address
Beech Tree Farm , Goveton , Kingsbridge , TQ7 2DT (Land between Goveton and A381)
Latitude
50.305269
Longitude
-3.749644
02

Companies

The source field combines operator and applicant roles; further entity resolution is planned.

Applicant or operatorCornwall Light and Power
03

Planning

Planning authority, reference and recorded milestones.

Planning authority
South Hams
Application reference
08_19/2525/07/F
Application submitted
30 Nov 2007
Permission granted
Not recorded

Project timeline

Planning application submitted

04

Generation & performance

Only reviewed BM-unit mappings and complete settlement periods are reported.

Not yet operational

Measured generation will only be considered after the project is operational and a BM-unit relationship is reviewed.

05

Sources & provenance

Trace every published field back to its current evidence.

Primary sourceRenewable Energy Planning Database

Department for Energy Security and Net Zero · July 2026

Record updated7 Dec 2010
Contains public sector information licensed under the Open Government Licence v3.0.